Prompt Payment. Payment shall be made in accordance with Chapter 2251 of the Texas Government Code, commonly known as the Texas Prompt Payment Act. Chapter 2251 of the Texas Government Code shall govern remittance of payment and remedies for late payment and non-payment.
Prompt Payment. All payments shall be governed as follows.
Prompt Payment. The State will pay the Contractor pursuant to Minn. Stat. § 16A.124, which requires payment within 30 days following receipt of an undisputed invoice, or merchandise or service, whichever is later. Terms requesting payment in less than 30 days will be changed to read “Net 30 days.” Notwithstanding the foregoing, the State may pay the Contractor in advance for purchases as allowed pursuant to Minn. Stat. §16A.065. The payment for each order will only be made for goods received or services actually performed that have been accepted by the ordering entity, and meet all terms, conditions, and specifications of the Contract and the ordering document.
Prompt Payment. (1) Any money, other than retainage, paid to the CONTRACTOR shall be disbursed to subcontractors within ten (10) days after receipt of the money in accordance with the terms of the subcontract; provided that the subcontractor has met all the terms and conditions of the subcontract and there are no bona fide disputes; and
(2) Upon final payment to the CONTRACTOR, full payment to the subcontractor, including retainage, shall be made within ten (10) days after receipt of the money; provided that there are no bona fide disputes over the subcontractor's performance under the subcontract.
Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:
(a) Progress Payments: 14 days
(b) Subsequent Subcontractor Payments: 7 days
Prompt Payment. The Contractor is required to pay its subcontractors performing work related to the Underlying Agreement for satisfactory performance of that work no later than 30 days after the Contractor’s receipt of payment for that work from County. In addition, the Contractor is required to return any retainage payments to those subcontractors within 30 days after the subcontractor’s work is satisfactorily completed.
Prompt Payment. Notwithstanding Paragraph 5, the Company shall comply with the requirements of Paragraphs 2 through 4 based on its interpretation of the appropriate payout. If the process described in Paragraph 5 results in a requirement for an additional payout, said payout shall be made no more than fourteen (14) days after the date of the agreed upon resolution or issuance of the arbitrator's decision.
Prompt Payment. Company must pay any of its subcontractor(s) who have submitted verified invoices for work already performed within ten (10) calendar days of being paid by Authority. Any exception to this prompt payment provision will only be for good cause with prior written approval of Authority. Failure of Company to pay any of its subcontractor(s) accordingly will be a material breach of this Contract.
Prompt Payment. The Borrower shall duly and punctually pay, or cause to be duly and punctually paid to the Finance Parties all amounts payable by each Obligor under the Finance Documents to which it is a party at the times and places and in the currency and manner mentioned therein.
Prompt Payment. Company agrees to pay each subcontractor under this Agreement for satisfactory performance of its agreement no later than ten (10) calendar days from the receipt of each payment that Company receives from the Authority. Company agrees further to release retainage payments to each subcontractor within ten (10) calendar days after the subcontractor’s work is satisfactorily completed. Any delay or postponement of payment from the above referenced time frame may occur only for good cause following written approval of the Authority. This clause applies to both W/MBE and non-W/MBE subcontractors.