Cost Allocation for Highway System Deliverability Upgrades. 12.1 If the portion of the Highway System Deliverability Upgrades (measured in MW) required to make one or more CRIS Projects in a Class Year deliverable is ninety percent (90%) or more of the total size (measured in MW) of the System Deliverability Upgrades, each Developer(s) of a Class Year CRIS Project(s) will be responsible for its pro rata Class Year share of one hundred percent (100%) of the cost of the System Deliverability Upgrades.
Appears in 2 contracts
Samples: Transmission Wheeling Agreements, Transmission Wheeling Agreements
Cost Allocation for Highway System Deliverability Upgrades. 12.1 If the portion of the Highway System Deliverability Upgrades (measured in MW) required to make one or more CRIS XXXX Projects in a Class Year deliverable is ninety percent (90%) or more of the total size (measured in MW) of the System Deliverability Upgrades, each Developer(s) of a Class Year CRIS XXXX Project(s) will be responsible for its pro rata Class Year share of one hundred percent (100%) of the cost of the System Deliverability Upgrades.
Appears in 2 contracts
Samples: Service Agreement for Firm Point to Point Transmission Service, Open Access Transmission Tariff (Oatt)
Cost Allocation for Highway System Deliverability Upgrades. 12.1 If the portion of the Highway System Deliverability Upgrades (measured in MW) required to make one or more CRIS Projects XXXX projects in a Class Year deliverable is ninety percent (90%) or more of the total size (measured in MW) of the System Deliverability Upgrades, each Developer(s) of a Class Year CRIS XXXX Project(s) will be responsible for its pro rata Class Year share of one hundred percent (100%) of the cost of the System Deliverability Upgrades.
Appears in 1 contract