COST RECORDS. 19.3.1 In all claims for changes to the Contract Sum or Guaranteed Maximum Price, the Construction Manager shall keep a correct accounting of the extra costs, in such reasonable form as the Principal Representative may require, and shall present such account, supported by receipts. The Principal Representative shall be entitled to reject any claim for extra costs if such documentation is not provided. 19.3.2 Any payments to the Construction Manager with respect to claims for increases in the Contract Sum or Guaranteed Maximum Price shall be limited to reimbursement for the additional expenditure by the Construction Manager, with the costs to be determined in accordance with paragraph 10.2 and the Construction Manager's Fee to be determined in accordance with paragraph 9.2.1, as limited and controlled by paragraph 6.4.2, when applicable.
Appears in 6 contracts
Samples: Construction Manager/General Contractor Agreement (Cmgc), Construction Manager/General Contractor Agreement, Construction Manager/General Contractor Agreement