Costs to Be Reimbursed. 6.1.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work as allowed in Paragraph 7.2
Appears in 2 contracts
Samples: Agreement Between Owner and Construction Manager, Agreement Between Owner and Construction Manager
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean costs reasonably and necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Contractor (Coast Hotels & Casinos Inc), Standard Form of Agreement Between Owner and Contractor (Coast Resorts Inc)
Costs to Be Reimbursed. 6.1.1 5.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 5.
Appears in 2 contracts
Samples: Abbreviated Form of Agreement Between Owner and Contractor for Construction Projects of Limited Scope (Roberts Realty Investors Inc), Abbreviated Form of Agreement Between Owner and Contractor (Roberts Realty Investors Inc)
Costs to Be Reimbursed. 6.1.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 6.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Construction Manager, Standard Form of Agreement Between Owner and Construction Manager (Mapinfo Corp)
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean all costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner, that are to be paid by Owner hereunder, and are subject to the Guaranteed Maximum price as described in clause 5.
2.1. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
Costs to Be Reimbursed. 6.1.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior consent to the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 6.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Construction Manager (Lifecore Biomedical Inc)
Costs to Be Reimbursed. 6.1.1 The term "7.1 Cost of the Work" Work The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Samples: Construction Contract
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" shall mean only those costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7. If a cost is covered by more than one provision of this Article 7, such cost shall be chargeable only once.
Appears in 1 contract
Samples: Construction Contract (National Instruments Corp /De/)
Costs to Be Reimbursed. 6.1.1 7.1 COST OF THE WORK The term "Cost of the Work" Work shall mean costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor (Skechers Usa Inc)
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean costs necessarily incurred by the Construction Manager contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor (Laboratory Specialists of America Inc)
Costs to Be Reimbursed. 6.1.1 9.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work as allowed which are actually paid by Contractor. Such costs shall not exceed the standard paid in Paragraph 7.2the locality of the Work except with the prior written consent of Owner. Such costs shall include the items set forth in this Article 9:
Appears in 1 contract
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean costs necessarily incurred by the Construction Manager Contractor in good faith and the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 7.
Appears in 1 contract
Samples: Contract for Construction
Costs to Be Reimbursed. 6.1.1 7.1 The term "Cost of the Work" Work shall mean costs necessarily incurred by the Construction Manager Contractor in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in this Article 7 and Paragraph 7.27.5.2
Appears in 1 contract
Costs to Be Reimbursed. 6.1.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager Operations Contractor in the proper performance of the Work. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior consent of the Owner. The Cost of the Work as allowed shall include only the items set forth in Paragraph 7.2this Article 6.