Decisions to Withhold Certification. § 9.5.1 The Owner may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner due to the Owner’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount that the Owner deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 12 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner due to the Owner’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount that the Owner deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss or damage for which the Design-Builder is responsible because of a dispute, including, but not limited to: .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Design-BuilderBuilder provided that, if applicable, the Owner has paid Design-Builder the sums that are the subject of such liens, claims, security interests, or encumbrances and Design-Builder has fully complied with all conditions for the payment of such sums; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner due to the Owner’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount that the Owner deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing remedied (150% of the estimated value of such claims unless security acceptable to the Owner is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the defective Work cannot may be completed for the unpaid balance of the Contract Sumwithheld);
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner Manager may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner Manager due to the OwnerManager’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner Manager is unable to certify payment in the amount of the Application, the Owner Manager will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner Manager cannot agree on a revised amount, the Owner Manager will promptly issue a Certificate for Payment for the amount that the Owner Manager deems to be due and owing. The Owner Manager may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner Manager from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner Manager is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Engineer, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner due to the Owner’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount that the Owner deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors Subcontractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner Manager may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner Manager due to the OwnerManager’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner Manager is unable to certify payment in the amount of the Application, the Owner Manager will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner Manager cannot agree on a revised amount, the Owner Manager will promptly issue a Certificate for Payment for the amount that the Owner Manager deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner Manager is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Engineer, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner due to the Owner’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount that the Owner deems to be due and owing. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance . Failure of the Contract SumDesign-Builder to make such payments shall not include withholding payment for unsatisfactory job progress, defective design or construction not remedied, or disputed work;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. DRAFT
§ 9.5.1 The Owner Manager may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner Manager due to the OwnerManager’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Design -Build Documents. If the Owner Manager is unable to certify payment in the amount of the Application, the Owner Manager will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner Manager cannot agree on a revised amount, the Owner Manager will promptly issue a Certificate for Payment for the amount that the Owner Manager deems to be due and owing. The Owner Manager may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner Manager from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner Manager is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Engineer, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
Decisions to Withhold Certification. § 9.5.1 The Owner Manager may withhold a Certificate for Payment in whole or in part to the extent reasonably necessary to protect the Owner Manager due to the OwnerManager’s determination that the Work has not progressed to the point indicated in the Design-Builder’s Application for Payment, or the quality of the Work is not in accordance with the Design-Build Documents. If the Owner Manager is unable to certify payment in the amount of the Application, the Owner Manager will notify the Design-Builder as provided in Section 9.4. If the Design-Builder and Owner Manager cannot agree on a revised amount, the Owner Manager will promptly issue a Certificate for Payment for the amount that the Owner Manager deems to be due and owing. The Owner Manager may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued to such extent as may be necessary to protect the Owner Manager from loss for which the Design-Builder is responsible because of .1 defective Work, including design and construction, not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner Manager is provided by the Design-Builder; .3 failure of the Design-Builder to make payments properly to the Architect, Consultants, Contractors or others, for services, labor, materials or equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder