Delays in the supplier’s performance. 22.1 Delivery of the Goods and performance of Services shall be made by the Supplier in accordance with the time schedule prescribed by the Purchaser in the Schedule of Requirements. 22.2 If at any time during performance of the Contract, the Supplier or its subcontractor(s) should encounter conditions impeding timely delivery of the Goods and performance of Services, the Supplier shall promptly notify the Purchaser in writing of the fact of the delay, its likely duration and its cause(s). As soon as practicable after receipt of the Supplier’s notice, the Purchaser shall evaluate the situation and may at its discretion extend the Supplier’s time for performance, with or without liquidated damages, in which case the extension shall be ratified by the parties by amendment of Contract. 22.3 Except as provided under GCC Clause 25, a delay by the Supplier in the performance of its delivery obligations shall render the Supplier liable to the imposition of liquidated damages pursuant to GCC Clause 23, unless an extension of time is agreed upon pursuant to GCC Clause 22.2 without the application of liquidated damages.
Appears in 2 contracts
Samples: Framework Contract, Framework Contract
Delays in the supplier’s performance. 22.1 18.1 Delivery of the Goods and and/or performance of Services shall be made by the Supplier in accordance with the time schedule prescribed by the Purchaser Procuring Entity in the Section VI. Schedule of RequirementsRequirement.
22.2 18.2 If at any time during the performance of the this Contract, the Supplier or its subcontractor(sSubcontractor(s) should encounter conditions impeding timely delivery of the Goods and and/or performance of Services, the Supplier shall promptly notify the Purchaser Procuring Entity in writing of the fact of the delay, its likely duration and its cause(s). As soon as practicable after receipt of the Supplier’s notice, and upon causes provided for under GCC Clause 22, the Purchaser Procuring Entity shall evaluate the situation and may at its discretion extend the Supplier’s time for performance, with or without liquidated damages, in which case the extension shall be ratified by the parties by amendment of Contract.
22.3 18.3 Except as provided under GCC Clause 2522, a delay by the Supplier in the performance of its delivery obligations shall render the Supplier liable to the imposition of liquidated damages pursuant to GCC Clause 2319, unless an Secretary Member Member extension of time is agreed upon pursuant to GCC Clause 22.2 29 without the application of liquidated damages.
Appears in 1 contract
Samples: General Conditions of Contract
Delays in the supplier’s performance. 22.1 21.1 Delivery of the Goods and performance of Services shall be made by the Supplier in accordance with the time schedule prescribed by the Purchaser / Bank in the Schedule of RequirementsTCC.
22.2 21.2 If at any time during performance of the Contract, the Supplier or its subcontractor(s) should encounter conditions impeding timely delivery of the Goods and performance of Services, the Supplier shall promptly notify the Purchaser Bank in writing of the fact of the delay, its it’s likely duration and its cause(s). As soon as practicable after receipt of the Supplier’s notice, the Purchaser Bank shall evaluate the situation and may may, at its discretion discretion, extend the Supplier’s Suppliers’ time for performance, with or without liquidated damages, in which case case, the extension shall be ratified by the parties by amendment of the Contract.
22.3 21.3 Except as provided under GCC Clause 25in the above clause, a delay by the Supplier in the performance of its delivery obligations shall render the Supplier liable to the imposition of liquidated damages pursuant to GCC Clause 23damages, unless an extension of time is agreed upon pursuant to GCC Clause 22.2 without the application of liquidated damages.
Appears in 1 contract
Samples: Terms and Conditions of Contract