Delivery of Request for Change Order. DB Contractor shall deliver a Request for Change Order under this Section 10.3.2.5 to TxDOT within 30 Days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order.
Appears in 13 contracts
Samples: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement
Delivery of Request for Change Order. DB Contractor shall deliver a Request for Change Order under this Section 10.3.2.5 to TxDOT within 30 Days days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order.
Appears in 1 contract
Samples: Comprehensive Maintenance Agreement