Department’s Review and Approval of Schedule Submissions. Department’s review and approval of the Preliminary, Baseline Schedule or subsequent Schedule Updates and Revised Baseline Schedule shall not be construed as relieving Design- Builder of its complete and exclusive control and responsibility over the means, methods, sequences and techniques for executing the Work and does not constitute approval or acceptance of Design-Builder’s ability to complete the Work within the Contract Time(s).
Appears in 5 contracts
Department’s Review and Approval of Schedule Submissions. Department’s review and approval of the PreliminaryPreliminary Schedule, Baseline Schedule or subsequent Schedule Updates and Revised Baseline Schedule shall not be construed as relieving Design- Design-Builder of its complete and exclusive control and responsibility over the means, methods, sequences and techniques for executing the Work and does not constitute approval or acceptance of Design-Design- Builder’s ability to complete the Work within the Contract Time(s)Times.
Appears in 4 contracts
Samples: Comprehensive Agreement, Comprehensive Agreement, Comprehensive Agreement
Department’s Review and Approval of Schedule Submissions. Department’s review and approval of the Preliminary, Baseline Schedule or subsequent Schedule Updates and Revised Baseline Schedule shall not be construed as relieving Design- Design-Builder of its complete and exclusive control and responsibility over the means, methods, sequences and techniques for executing the Work and does not constitute approval or acceptance of Design-Builder’s ability to complete the Work within the Contract Time(s).
Appears in 1 contract
Samples: Comprehensive Agreement