Common use of Dependable Capacity Test Clause in Contracts

Dependable Capacity Test. The Dependable Capacity Test shall be carried out to determine the Dependable Capacity of the Facility during Commissioning pursuant to Section 7. The Dependable Capacity of the Facility shall be determined to be equal to, or greater than the Contracted Capacity, calculated at the generating points, using calibrated test metering equipment. The test (“Dependable Capacity Test”) will be conducted for a minimum of 3 (three) consecutive hours. The Dependable Capacity shall be determined by the following method:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement