Design. 4.2.1 Seller, at no cost to Edison, shall: a. Design the Generating Facility. b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility. c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility. d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system. 4.2.2 Edison shall have the right to: a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice. b. Request modifications to the design of the Generating Facility's electrical system and the Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system. 4.2.3 If Seller's Generating Facility includes an induction-type generator(s), Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type generator(s) of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
Appears in 2 contracts
Samples: Power Purchase Contract (Ormat Technologies, Inc.), Power Purchase Contract (Ormat Technologies, Inc.)
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.
4.2.2 Edison shall have the right to:
a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If Seller's Generating Facility includes an induction-type generator(s), Seller shall provide individual power factor correction capacitors for each such induction-type generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type generator(s) of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
4.2.4 Seller shall not locate any part of a wind-driven generating unit of the Generating Facility within a distance 1.25 times the height of a wind turbine structure of an existing electric utility 33 kV, 66 kV, or 115 kV transmission line right of way or within three rotor blade diameters of an existing electric utility 220 kV or 500 kV transmission line right of way or any proposed transmission line right of way of which Edison is pursuing regulatory approval for construction.
Appears in 2 contracts
Samples: Power Purchase Contract (Zond Windsystem Partners LTD Series 85-B), Power Purchase Contract (Zond Windsystem Partners LTD Series 85-A)
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall SCE STANDARD CONTRACT LONG-TERM POWER PURCHASE be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.
4.2.2 Edison shall have the right to:
a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If Seller's Generating Facility includes an induction-type generator(s), Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type SCE STANDARD CONTRACT LONG-TERM POWER PURCHASE generator(s) of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
Appears in 2 contracts
Samples: Power Purchase Contract (Ormat Technologies, Inc.), Power Purchase Contract (Ormat Technologies, Inc.)
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.. //
4.2.2 Edison shall have the right to:
a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If Seller's Generating Facility includes an induction-type generator(s), Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type generator(s) of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
4.2.4 Seller shall not locate any part of a wind-driven generating unit of the Generating Facility within a distance
Appears in 2 contracts
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies studies, necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.
4.2.2 Edison shall have the right to:
a. Review review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If if Seller's Generating Facility includes an induction-type generator(s)generators, Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type induction'-type generator(s) of the Generating Facility. .. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
4.2.4 Seller shall not locate any part of a wind-driven generating unit of the Generating Facility within a distance 1.25 times the height of a wind turbine structure of an existing electric utility 33 kV, 66 kV, or 115 kV transmission line right of way or within three rotor blade diameters of an existing electric utility 220 kV or 500 kV transmission line right of way or any proposed transmission line right of way of which Edison is pursuing regulatory approval for construction.
4.2.5 If Seller's Generating Facility is a small hydro project, the Contract Capacity in Section 1.5 shall be based on the average of the 5 lowest years of stream flow taken from a study covering a minimum 50 years of continuous data. The Parties may agree upon a shorter period if data for a 50-year period is not obtainable.
Appears in 1 contract
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.. //
4.2.2 Edison shall have the right to:
a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If Seller's Generating Facility includes an induction-type generator(s), Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated induction-type generator(s) of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
4.2.4 Seller shall not locate any part of a wind-driven generating unit of the Generating Facility within a distance 1.25 times the height of a wind turbine structure of an existing electric utility 33 kV, 66 kV, or 115 kV transmission line right of way or within three rotor blade diameters of an existing electric utility 220 kV or 500 kV transmission line right of way or any proposed transmission line right of way of which Edison is pursuing regulatory approval for construction.
4.2.5 If Seller's Generating Facility is a small hydro project, the Contract Capacity in Section 1.5 shall be based on the average of the 5 lowest years of stream flow taken from a study covering a minimum 50 years of continuous data. The Parties may agree upon a shorter period if data for a 50-year period is not obtainable.
Appears in 1 contract
Samples: Power Purchase Contract
Design. 4.2.1 Seller, at no cost to Edison, shall:
a. Design the Generating Facility.
b. Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Generating Facility.
c. Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Generating Facility.
d. Furnish and install the relays, meters, power circuit breakers, synchronizer, and other control and Protective Apparatus as shall be agreed to by the Parties as being necessary for proper and safe operation of the Project in parallel with Edison's electric system.
4.2.2 Edison shall have the right to:
a. Review the design of the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such review may include, but not be limited to, the Generator, governor, excitation system, synchronizing equipment, protective relays, and neutral grounding. The Seller shall be notified in writing of the outcome of the Edison review within 30 days of the receipt of all specifications for both the Generating Facility and the Interconnection Facilities. Any flaws perceived by Edison in the design shall be described in Edison's written notice.
b. Request modifications to the design of of. the Generating Facility's electrical system and the Seller's Interconnection Facilities. Such modifications shall be required if necessary to maintain Edison Electric System Integrity when in parallel with the Edison electric system.
4.2.3 If Seller's Generating Facility includes an induction-type generator(s)generators, Seller shall provide individual power factor correction capacitors for each such generator. Such capacitors shall be switched on and off simultaneously with each of the associated associated', induction-type generator(s) generators of the Generating Facility. The KVAR rating of such capacitors shall be the highest standard value which will not exceed such generators no-load KVAR requirement. Seller shall not install power factor correction in excess of that required by this Section unless agreed to in writing by the Parties.
4.2.4 Seller shall not locate any part of a wind-driven generating unit of the Generating Facility within a distance 1.25 times the height of a wind turbine structure of an existing electric utility 33 kV, 66 kV, or 115 kV transmission line right of way or within three rotor blade diameters of an existing electric utility 220 kV or 500 kV transmission line right of way or any proposed transmission line right of way of which Edison is pursuing regulatory approval for construction.
4.2.5 If Seller's Generating Facility is a small hydro project, the Contract Capacity in Section 1.5 shall be based on the average of the 5 lowest years of stream flow taken from a study covering a minimum 50 years of continuous data. The Parties may agree upon a shorter period if data for a 50-year period is not obtainable.