Common use of Detailed Claim Clause in Contracts

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 31 contracts

Samples: Professional Services, Professional Services, Professional Services

AutoNDA by SimpleDocs

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment completion of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 18 contracts

Samples: Professional Services, Professional Services, Professional Services

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 8 contracts

Samples: Personal Services Agreement, Personal Services Agreement, Interlocal Agreement

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the CountyCity, the Contractor has given the County City a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 6 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each eac h element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 2 contracts

Samples: Professional Services, Professional Services

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before the final payment by the CountyCity, the Contractor has given the County City a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 2 contracts

Samples: Construction Contract, Contract for Services

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment completion of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 2 contracts

Samples: Personal Services Agreement, Personal Services Agreement

AutoNDA by SimpleDocs

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the CountyDistrict, the Contractor has given the County District a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 2 contracts

Samples: Personal Services Agreement, Personal Services Agreement

Detailed Claim. The Contractor shall is not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.

Appears in 1 contract

Samples: Professional Services

Detailed Claim. The Contractor shall not be entitled to claim any such additional compensation, or extension of time, unless within thirty (30) 30 days of the accomplishment of the portion of the work from which the claim arose, and before final payment by the County, the Contractor has given the County a detailed written statement of each element of cost or other compensation requested and of all elements of additional time required, and copies of any supporting documents evidencing the amount or the extension of time claimed to be due.. KPHD 2046 PERSONAL SERVICES AGREEMENT ATTACHMENT C