Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals. 10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values. 10.1.1 Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.] 10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District. 10.1.3 The District will review the schedules submitted and Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District. 10.1.4 The District shall have the right at any time to discuss with Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed. 10.1.5 All schedules must be approved by the District before Developer can rely on them as a basis for payment. 10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 35 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. e.g., Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 4 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 The Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and the Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with the Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All submittals and schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), the Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 4 contracts
Samples: Facilities Lease, Facilities Lease, General Construction Agreement
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 The Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and the Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with Developer revisions to revise the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All submittals and schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), the Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 3 contracts
Samples: General Construction Agreement, Facilities Lease, Facilities Lease
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer shall be responsible for the development of schedule, cost and resource loading of the schedule, monthly payment requests, and project status reporting requirements of the Contract shall employ computerized Critical Path Method (“CPM”) scheduling (“CPM Schedule”). CPM Schedule shall be cost loaded based on Schedule of Values as approved by District.
10.1.3 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 10.1.4 The District will review the schedules submitted and Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 10.1.5 The District shall have the right at any time to discuss with Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 10.1.6 All schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 10.1.7 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 2 contracts
Samples: General Construction Agreement, General Construction Agreement
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 2 contracts
Samples: Construction Contract, General Construction Agreement
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All submittals and schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require:
Appears in 2 contracts
Samples: General Construction Agreement, General Construction Agreement
Developer’s Submittals and Schedules. Developer’s submittals shall comply with the provisions and requirements of the Specifications including, without limitation Submittals.
10.1 Schedule of Work, Schedule of Submittals, and Schedule of Values.
10.1.1 The Developer shall comply with the construction schedule attached to the Facilities Lease as Exhibit F (“Construction Schedule”). [To be attached when available.]
10.1.2 Developer must provide all schedules both in hard copy and electronically, electronically in a native format (e.g. Microsoft Project or Primavera) approved in advance by the District.
10.1.3 The District will review the schedules submitted and the Developer shall make changes and corrections in the schedules as requested by the District and resubmit the schedules until approved by the District.
10.1.4 The District shall have the right at any time to discuss with the Developer revisions to the schedule of values if, in the District's sole opinion, the schedule of values does not accurately reflect the value of the Work performed.
10.1.5 All submittals and schedules must be approved by the District before Developer can rely on them as a basis for payment.
10.1.6 Within TEN (10) calendar days after the date of the Notice to Proceed with Construction (unless otherwise specified in the Specifications), the Developer shall prepare and submit to the District for review, in a form supported by sufficient data to substantiate its accuracy as the District may require: