Effect of Force Majeure Event on the Procurement Contract. 17.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event. 17.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier is unable to transmit electricity to the Grid despite making best efforts or it is directed by the Utility, RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 6 contracts
Samples: Procurement Agreement, Procurement Agreement, Procurement Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 16.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 16.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier is unable to transmit electricity to the Grid Drawal Point despite making best efforts or it is directed by the UtilityAggregator , RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility Aggregator shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 3 contracts
Samples: Procurement Agreement, Procurement Agreement, Procurement Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 15.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier Aggregator is unable to transmit electricity to the Grid Drawal Point despite making best efforts or it is directed by the UtilityUtility , RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier Aggregator was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier Aggregator to extension of 1 (one) day in the Contract Period.
Appears in 3 contracts
Samples: Power Supply Agreement, Power Supply Agreement, Power Supply Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 17.5.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 17.5.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon where upon the Supplier is unable to transmit electricity to the Grid despite making best efforts or it is directed by the UtilityGRIDCO, RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility GRIDCO shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four4(four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Procurement Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier Aggregator is unable to transmit electricity to the Grid despite making best efforts or it is directed by the Utility, RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier Aggregator was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier Aggregator to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Power Supply Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 16.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 16.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier Concessionaire is unable to transmit electricity to the Grid despite making best efforts or it is directed by the UtilityMCGM, RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier Concessionaire was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility MCGM shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier Concessionaire to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Power Procurement Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 17.5.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 17.5.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier is unable to transmit electricity to the Grid despite Griddespite making best efforts or it is directed by the Utility, RLDC or RLDCor SLDC or any Government Instrumentality to suspend generation or transmission ortransmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability theAvailability on any day is to decline below 80below80% (eighty per cent) of the Normative Availability, the Utility shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty twenty-five per cent) of Availability for 4 (four4(four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Power Purchase Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 15.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier Aggregator is unable to transmit electricity to the Grid Delivery Point despite making best efforts or it is directed by the UtilityUtility , RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier Aggregator was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier Aggregator to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Power Supply Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier is unable to transmit electricity to the Grid despite making best efforts or it is directed by the UtilityAggregator, RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability partialinability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility Aggregator shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 1 contract
Samples: Procurement Agreement
Effect of Force Majeure Event on the Procurement Contract. 17.6.1 16.6.1 Upon the occurrence of any Force Majeure Event prior to the Appointed Date, the period set forth in Clause 4.1 for fulfilment of Conditions Precedent shall be extended by a period equal in length to the duration of the Force Majeure Event.
17.6.2 16.6.2 If any force Majeure Event occurs at any time after the Appointed Date, whereupon the Supplier is unable to transmit electricity to the Grid Delivery Point despite making best efforts or it is directed by the UtilityAggregator , RLDC or SLDC or any Government Instrumentality to suspend generation or transmission during the subsistence of such Force Majeure Event, the Contract Period shall be extended by a period equal in length to the period during which the Supplier was prevented from generating or transmitting electricity on account thereof; provided that in the event of reduction in generation on account of partial inability or suspension, as the case may be, which cause the Availability on any day is to decline below 80% (eighty per cent) of the Normative Availability, the Utility Aggregator shall extend the Contract Period in proportion to the loss of Availability due to Force Majeure. For the avoidance of doubt, loss of 25% (twenty five per cent) of Availability for 4 (four) days shall entitle the Supplier to extension of 1 (one) day in the Contract Period.
Appears in 1 contract