Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design of 5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and 5.5.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 19 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design ofto
5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and
5.5.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 6 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design of
5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and
5.5.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 11.5 by the dates specified in Appendix B, Milestones.
Appears in 2 contracts
Samples: Generator Interconnection Agreement, Provisional Generator Interconnection Agreement
Equipment Procurement. If responsibility for construction of the Interconnecting Transmission Owner’s Interconnection Facilities, Facilities or Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then by
5.5.1 The Interconnecting Transmission Owner shall commence design of
5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and
5.5.2 Where applicable, The Interconnecting Transmission Owner has received written authorization to proceed with design and procurement from the Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates date specified in Appendix B, B (Milestones).
Appears in 1 contract
Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design ofto
5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and
5.5.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 11.5 by the dates specified in Appendix B, Milestones.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Equipment Procurement. If responsibility for construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or Distribution Upgrades is to be borne by Transmission Owner, then Transmission Owner shall commence design ofof the Transmission Owner’s Interconnection Facilities, Network Upgrades and/or
5.5.1 Transmission Provider has completed the Interconnection Facilities Study pursuant to the Interconnection Facilities Study Agreement; and
5.5.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 1 contract
Samples: Generator Interconnection Agreement