Equitable Adjustments. 8.2.1. If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement will be modified in writing accordingly. Every Change Order may require a cost analysis to determine the reasonableness of the proposed change. 8.2.2. All changes to the Agreement that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor. 8.2.3. Any claim by Contractor for an equitable adjustment under this Section 8.2.4. No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor gives written notice, as required in this section. 8.2.5. Contractor shall continue to perform the Services in accordance with this Agreement, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18, Dispute Resolution.
Appears in 10 contracts
Samples: Contract Agreement, Contract Agreement, Fleet Cleaning and Disinfecting Services Agreement
Equitable Adjustments. 8.2.1. a) If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement Contract will be modified in writing accordingly. Every Change Order may require a cost analysis to determine deter- mine the reasonableness of the proposed change.
8.2.2. b) All changes to the Agreement Contract that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor.
8.2.3. c) Any claim by Contractor for an equitable adjustment under this SectionSection 14 must be asserted within 14 calendar days from the date of receipt by Contractor of the notification of change. The request for equitable adjustment must be in writing and state the general nature and monetary extent of the claim. The Contract Administrator may require additional supporting documents and cost or price analysis to determine the validity of the claim.
8.2.4. d) No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor Con- tractor gives written notice, as required in this section.
8.2.5. e) Contractor shall continue to perform the Services in accordance with this AgreementContract, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute consti- tute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18Section 46, Dispute Resolution.Resolution of this Exhibit E.
Appears in 4 contracts
Samples: Supply Contract, Supply Contract, Supply Contract
Equitable Adjustments. 8.2.1. If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement will be modified in writing accordingly. Every Change Order may require a cost analysis to determine the reasonableness of the proposed change.
8.2.2. All changes to the Agreement that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor.
8.2.3. Any claim by Contractor for an equitable adjustment under this SectionSection 8.2 must be asserted within 14 calendar days from the date of receipt by Contractor of the notification of change. The request for equitable adjustment must be in writing and state the general nature and monetary extent of the claim. The Contract Administrator may require additional supporting documents and cost or price analysis to determine the validity of the claim.
8.2.4. No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor gives written notice, as required in this section.
8.2.5. Contractor shall continue to perform the Services in accordance with this Agreement, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18, Dispute Resolution.
Appears in 2 contracts
Samples: Shelter Removal and Installation Services Agreement, General Cleaning and Trash Removal Services Agreement
Equitable Adjustments. 8.2.1. If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement will be modified in writing accordingly. Every Change Order may require a cost analysis to determine the reasonableness of the proposed change.
8.2.2. All changes to the Agreement that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor.
8.2.3. Any claim by Contractor for an equitable adjustment under this Section
8.2.4. No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor gives written notice, as required in this section.
8.2.5. Contractor shall continue to perform the Services in accordance with this Agreement, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18, Dispute Resolution.in
Appears in 2 contracts
Samples: Fleet Cleaning and Disinfecting Services Agreement, Construction Services Agreement
Equitable Adjustments. 8.2.1. If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement will be modified in writing accordingly. Every Change Order may require a cost analysis to determine the reasonableness of the proposed change.
8.2.2. All changes to the Agreement that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor.
8.2.3. Any claim by Contractor for an equitable adjustment under this Section
8.2.4. No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor gives written notice, as required in this section.any
8.2.5. Contractor shall continue to perform the Services in accordance with this Agreement, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18, Dispute Resolution.
Appears in 2 contracts
Samples: Landscaping and Lawn Service Agreement, Janitorial Services Agreement
Equitable Adjustments. 8.2.1. If any Change Order results in an increase or decrease in the Charges or time required to perform the Services, an equitable adjustment will be made, at the sole discretion of GRTC, to the Charges, schedule or both, and the Agreement will be modified in writing accordingly. Every Change Order may require a cost analysis to determine the reasonableness of the proposed change.
8.2.2. All changes to the Agreement that are a result of legislation or regulations that become effective after the date of proposal and prior to final completion, which might require an adjustment to the Charges, upward or downward, shall be evaluated by both parties. An adjustment to the Charges shall be negotiated between the Contract Administrator and the designated representative of Contractor.
8.2.3. Any claim by Contractor for an equitable adjustment under this Section
8.2.4. No claim by Contractor for an equitable adjustment hereunder will be allowed if asserted after final payment under this Agreement. No claim will be allowed for any costs incurred more than 20 calendar days before Contractor gives written notice, as required in this section.
8.2.5. Contractor shall continue to perform the Services in accordance with this Agreement, without delay or interruption, during any period that GRTC is considering a request for an equitable adjustment and during the pendency of any dispute over an equitable adjustment. GRTC shall notify Contractor of its decision regarding the equitable adjustment in writing. Failure by GRTC and Contractor to agree upon an equitable adjustment shall not constitute a basis for Contractor to suspend performance of the Services but shall be resolved pursuant to Article 18R, Dispute Resolution.
Appears in 1 contract
Samples: Transit Rideship Survey Agreement