Executed Change Orders Final. The Contractor agrees that any Change Order executed by the Department and Contractor constitutes its full and final adjustment for all costs, delays, disruptions, inefficiencies, accelerations, schedule impacts, or other consequences arising from the change in question, whether a Change Directive, or a Change Event, or from any claimed cumulative effect of changes made to the date of the Change Order, and that no further adjustments in compensation or time shall be sought or made with respect to the Change Directive or the Change Event giving rise to the Change Order.
Appears in 10 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement
Executed Change Orders Final. The Contractor A/E agrees that any Change Order executed by the Department and Contractor the A/E constitutes its full and final adjustment for all costs, delays, disruptions, inefficiencies, accelerations, schedule impacts, or other consequences arising from the change in question, whether a Change Directive, or a Change Event, or from any claimed cumulative effect of changes made to the date of the Change Order, and that no further adjustments in compensation or time shall be sought or made with respect to the Change Directive or the Change Event giving rise to the Change Order.
Appears in 3 contracts
Sources: Architectural/Engineering Services Agreement, Architectural/Engineering Services Agreement, Architectural/Engineering Services Agreement
Executed Change Orders Final. The Contractor A/E agrees that any Change Order executed by the Department and Contractor the A/E constitutes its full and final adjustment for all costs, delays, disruptions, inefficiencies, accelerations, schedule impacts, or other consequences arising from the change in question, whether a Change Directive, or a Change Event, or from any claimed cumulative effect of changes made to the date of the Change Order, and that no further adjustments in compensation or time shall be sought or made with respect to the Change Directive or the Change Event giving rise to the Change Order.Directive
Appears in 2 contracts
Sources: Architectural/Engineering Services Agreement, Agreement for Architectural/Engineering Services
Executed Change Orders Final. The Contractor agrees that any Change Order executed by the Department and the Contractor constitutes its full and final adjustment for all costs, delays, disruptions, inefficiencies, cumulative impact, accelerations, schedule impacts, or other consequences arising from the change in question, whether a Change Directive, or a Change Event, or from any claimed cumulative effect of changes made to the date of the Change Order, and that no further adjustments in compensation or time shall be sought or made with respect to the Change Directive or the Change Event giving rise to the Change Order.
Appears in 2 contracts
Sources: Telecommunications Services Agreement, Strategic Management Consulting Services Agreement
Executed Change Orders Final. The Contractor agrees that any Change Order executed by the Department and the Contractor constitutes its full and final adjustment for all costs, delays, disruptions, inefficiencies, cumulative impact, accelerations, schedule impacts, or other consequences arising from the change in question, whether a Change Directive, or a Change Event, or from any claimed cumulative effect of changes made to the date of the Change Order, and that no further adjustments in compensation or time shall be sought or made with respect to the Change Directive or the Change Event giving rise to the Change Order.
Appears in 2 contracts
Sources: Contract for Snow and Ice Removal and Pretreatment Services, Contract