Extension of Time not Cumulative. In case the Design-Build Firm shall be delayed for any period of time by two or more of the causes mentioned in Article 68, Excusable Delays the Design-Build Firm shall not be entitled to a separate extension for each one of the causes; only one period of extension shall be granted for the delay.
Appears in 3 contracts
Samples: archive.miamigov.com, archive.miamigov.com, ci.miami.fl.us
Extension of Time not Cumulative. In case the Design-Build Firm shall be delayed for any period of time by two or more of the causes mentioned in Article 6870, Excusable Delays Excusable, Delays, the Design-Build Firm shall not be entitled to a separate extension for each one of the causes; only one period of extension shall be granted for the delay.
Appears in 1 contract
Samples: ci.miami.fl.us