Extension of Time not Cumulative. In case the Design-Build Firm shall be delayed for any period of time by two or more of the causes mentioned in Article 68, Excusable Delays the Design-Build Firm shall not be entitled to a separate extension for each one of the causes; only one period of extension shall be granted for the delay.
Appears in 3 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Services Agreement
Extension of Time not Cumulative. In case the Design-Build Firm shall be delayed for any period of time by two or more of the causes mentioned in Article 6870, Excusable Delays Excusable, Delays, the Design-Build Firm shall not be entitled to a separate extension for each one of the causes; only one period of extension shall be granted for the delay.