Extension of Time not Cumulative. 7.11.1 In case the Contractor shall be delayed at any time or for any period by two or more causes for an extension of time, the Contractor shall not be entitled to a separate extension of time for each one of the causes but only one period of extension will be granted for the delay.
Appears in 2 contracts
Samples: Construction Services Agreement, Construction Services Agreement
Extension of Time not Cumulative. 7.11.1 In case the Contractor shall be delayed at any time or for any period of time by two or more of the causes for an extension of timementioned in Article 69, Excusable, Delays, the Contractor shall not be entitled to a separate extension of time for each one of the causes but causes; only one period of extension will shall be granted for the delay.
Appears in 1 contract
Samples: Design and Construction Agreement
Extension of Time not Cumulative. 7.11.1 In case the Contractor shall be delayed at any time or for any period of time by two or more of the causes for an extension of timementioned in Article 67, Excusable, Delays, Non-Compensable, the Contractor shall not be entitled to a separate extension of time for each one of the causes but causes; only one period of extension will shall be granted for the delay.
Appears in 1 contract