Extension of Timelines for Delivery. The dates set forth in Section 4.1.1 for the delivery of all plans, specifications and other documents and materials relating to the Hotels (collectively, the “Review Materials”) may be extended as necessary by agreement of the parties, and shall be extended for a Force Majeure event in accordance with Section 13.12; provided, however, no such extension shall be granted unless Manager is provided with notice of such delay at least 14 days prior to the required due date (except for events which occur within the 14 day period prior to the due date, in which case, Owner shall notify Manager of any anticipated delay as soon as reasonably possible following such Force Majeure).
Appears in 4 contracts
Samples: Technical Services Agreement, Technical Services Agreement, Technical Services Agreement