Common use of Failure of Contractor to Perform Warranty Work Clause in Contracts

Failure of Contractor to Perform Warranty Work. If Contractor does not use its reasonable efforts to proceed to complete the Warranty work, or cause any relevant Subcontractor to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 16, Owner shall provide Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s intent to perform itself or cause to be performed by third parties, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary work or have third parties perform such work and Contractor shall bear the reasonable costs thereof (plus seven percent (7%) of such costs as an allowance for overhead and related costs); provided that Contractor shall be given the opportunity to observe, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this Agreement. If any of the Work fails to satisfy the applicable Warranty during the applicable Warranty Period and any such failure occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor; provided that, if practicable, Owner provides reasonably prompt Notice to Contractor of such immediate need prior to performing such Warranty work and, if reasonably practicable, gives Contractor the opportunity to perform such Warranty work.

Appears in 3 contracts

Samples: And Construction Agreement, And Construction Agreement (Powersecure International, Inc.), And Construction Agreement (Powersecure International, Inc.)

AutoNDA by SimpleDocs

Failure of Contractor to Perform Warranty Work. If Contractor does not use its reasonable efforts to proceed to complete the Warranty work, or cause any relevant Subcontractor to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 16, Owner shall provide Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s intent to perform itself or cause to be performed by third parties, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary work or have third parties perform such work and Contractor shall bear the reasonable costs thereof (plus seven percent (7%) of such costs as an allowance for overhead and related costs); provided that Contractor shall be given the opportunity to observe, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope Statement of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this Agreement. If any of the Work fails to satisfy the applicable Warranty during the applicable Warranty Period and any such failure occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor; provided that, if practicable, Owner provides reasonably prompt Notice to Contractor of such immediate need prior to performing such Warranty work and, if reasonably practicable, gives Contractor the opportunity to perform such Warranty work.

Appears in 3 contracts

Samples: Procurement and Construction Agreement (Powersecure International, Inc.), Procurement and Construction Agreement (Powersecure International, Inc.), Procurement and Construction Agreement (Powersecure International, Inc.)

Failure of Contractor to Perform Warranty Work. If after Block Substantial Completion, Contractor does not use its reasonable efforts to proceed to complete the applicable Warranty work, or cause any relevant Subcontractor or Supplier to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 1621 in accordance with the terms hereof, Owner shall provide shall, after giving Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s 's intent to perform the remedial Warranty work itself or cause at least *** prior to be performed by third partiesOwner's commencement of any such remedial Warranty work, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary Warranty work to remedy the Warranty claim, or have third parties perform such the necessary Warranty work and Contractor shall bear the reasonable costs thereof thereof. If Contractor (plus seven percent (7%or the relevant Subcontractor or Supplier) implements a plan to diligently perform the Warranty work to satisfy such Warranty claim during such *** period, and thereafter diligently prosecutes the execution of such costs as an allowance for overhead and related costs); provided that Contractor plan, Owner shall be given the opportunity not perform, or cause any third party to observeperform, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this AgreementWarranty work. If any of the Work fails a defect or other nonconformance to satisfy the applicable Warranty arises during the applicable Warranty Period and any such failure defect or nonconformance occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor's account; provided thatprovided, if practicablehowever, that upon completion of such work, Owner provides reasonably prompt Notice shall provide Contractor notice of, and an opportunity to Contractor of such immediate need prior to performing inspect, such Warranty work. Within *** after receiving the notice referenced in the preceding sentence, Contractor shall inspect such work andperformed by Owner and either (i) ratify Owner's work or (ii) elect to repair or otherwise correct Owner's work. In the event that Contractor elects to proceed pursuant to sub-clause (ii), if reasonably practicableContractor shall complete such work, gives Contractor as necessary under the opportunity circumstances, with reasonable promptness. If Owner performs or causes third parties to perform such Warranty work as set forth above, Owner shall provide reasonable access to Contractor to the Facility to observe Owner's and its Affiliates' or any third party's performance of the Warranty work. The performance of Warranty work, either performed by Owner or performed by third parties engaged by Owner which was performed in accordance with the applicable provisions of this Agreement related to such Warranty work that Contractor, had it performed the Warranty work itself, would have observed to comply with this Agreement, shall be deemed covered by the Warranties, and Contractor shall reimburse Owner for all reasonable costs, charges and expenses incurred by Owner in connection therewith plus ***.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement (Sunpower Corp), Engineering, Procurement and Construction Agreement (Sunpower Corp)

Failure of Contractor to Perform Warranty Work. If after Block Substantial Completion, Contractor does not use its reasonable efforts to proceed to complete the applicable Warranty work, or cause any relevant Subcontractor or Supplier to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 1621 in accordance with the terms hereof, Owner shall provide shall, after giving Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s 's intent to perform the remedial Warranty work itself or cause at least three (3) Business Days prior to be performed by third partiesOwner's commencement of any such remedial Warranty work, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary Warranty work to remedy the Warranty claim, or have third parties perform such the necessary Warranty work and Contractor shall bear the reasonable costs thereof thereof. If Contractor (plus seven percent or the relevant Subcontractor or Supplier) implements a plan to diligently perform the Warranty work to satisfy such Warranty claim during such three (7%3) Business Day period, and thereafter diligently prosecutes the execution of such costs as an allowance for overhead and related costs); provided that Contractor plan, Owner shall be given the opportunity not perform, or cause any third party to observeperform, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this AgreementWarranty work. If any of the Work fails a defect or other nonconformance to satisfy the applicable Warranty arises during the applicable Warranty Period and any such failure defect or nonconformance occurs under circumstances where *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor's account; provided thatprovided, if practicablehowever, that upon completion of such work, Owner provides reasonably prompt Notice shall provide Contractor notice of, and an opportunity to Contractor of such immediate need prior to performing inspect, such Warranty work. Within seven (7) Days after receiving the notice referenced in the preceding sentence, Contractor shall inspect such work andperformed by Owner and either (i) ratify Owner's work or (ii) elect to repair or otherwise correct Owner's work. In the event that Contractor elects to proceed pursuant to sub-clause (ii), if reasonably practicableContractor shall complete such work, gives Contractor as necessary under the opportunity circumstances, with reasonable promptness. If Owner performs or causes third parties to perform such Warranty work as set forth above, Owner shall provide reasonable access to Contractor to the Facility to observe Owner's and its Affiliates' or any third party's performance of the Warranty work. The performance of Warranty work, either performed by Owner or performed by third parties engaged by Owner which was performed in accordance with the applicable provisions of this Agreement related to such Warranty work that Contractor, had it performed the Warranty work itself, would have observed to comply with this Agreement, shall be deemed covered by the Warranties, and Contractor shall reimburse Owner for all reasonable costs, charges and expenses incurred by Owner in connection therewith plus *** percent (***%).

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)

Failure of Contractor to Perform Warranty Work. If after Substantial Completion, Contractor does not use its reasonable efforts to proceed to complete the applicable Warranty work, or cause any relevant Subcontractor to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 1621 in accordance with the terms hereof, Owner shall provide shall, after giving Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s intent to perform the remedial Warranty work itself or cause at least three (3) Business Days prior to be performed by third partiesOwner’s commencement of any such remedial Warranty work, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary Warranty work to remedy the Warranty claim, or have third parties perform such the necessary Warranty work and Contractor shall bear the reasonable costs thereof thereof. If Contractor (plus seven percent or the relevant Subcontractor) implements a plan to diligently perform the Warranty work to satisfy such Warranty claim during such three (7%3) Business Day period, and thereafter diligently prosecutes the execution of such costs as an allowance for overhead and related costs); provided that Contractor plan, Owner shall be given the opportunity not perform, or cause any third party to observeperform, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this AgreementWarranty work. If any of the Work fails a defect or other nonconformance to satisfy the applicable Warranty arises during the applicable Warranty Period and any such failure defect or nonconformance occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor; provided that, if practicable, account. If Owner provides reasonably prompt Notice to Contractor of such immediate need prior to performing such Warranty work and, if reasonably practicable, gives Contractor the opportunity performs or causes third parties to perform such Warranty work as set forth above, Owner shall provide reasonable access to Contractor to the Facility to observe Owner’s and its Affiliates’ or any third party’s performance of the Warranty work. The performance of Warranty work, either performed by Owner or performed by third parties engaged by Owner which was performed in accordance with the applicable provisions of this Agreement related to such Warranty work that Contractor, had it performed the Warranty work itself, would have observed to comply with this Agreement, shall be deemed covered by the Warranties, and Contractor shall reimburse Owner for all reasonable costs, charges and expenses incurred by Owner in connection therewith, which shall include a ten percent (10%) xxxx-up. For clarity, Contractor may not rely upon the failure of any Subcontractor to honor its warranty obligations to excuse or limit Contractor’s Warranties. At Owner’s election, it may apply any Retainage being held under Section 8.1(c) toward any costs for which Contractor is responsible hereunder. Enforcement by Owner.

Appears in 1 contract

Samples: Procurement and Construction Agreement

AutoNDA by SimpleDocs

Failure of Contractor to Perform Warranty Work. If after Block Substantial Completion, Contractor does not use its reasonable efforts to proceed to complete the applicable Warranty work, or cause any relevant Subcontractor or Supplier to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 1621 in accordance with the terms hereof, Owner shall provide shall, after giving Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s 's intent to perform the remedial Warranty work itself or cause at least three (3) Business Days prior to be performed by third partiesOwner's commencement of any such remedial Warranty work, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary Warranty work to remedy the Warranty claim, or have third parties perform such the necessary Warranty work and Contractor shall bear the reasonable costs thereof thereof. If Contractor (plus seven percent or the relevant Subcontractor or Supplier) implements a plan to diligently perform the Warranty work to satisfy such Warranty claim during such three (7%3) Business Day period, and thereafter diligently prosecutes the execution of such costs as an allowance for overhead and related costs); provided that Contractor plan, Owner shall be given the opportunity not perform, or cause any third party to observeperform, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this AgreementWarranty work. If any of the Work fails a defect or other nonconformance to satisfy the applicable Warranty arises during the applicable Warranty Period and any such failure defect or nonconformance occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor's account; provided thatprovided, if practicablehowever, that upon completion of such work, Owner provides reasonably prompt Notice shall provide Contractor notice of, and an opportunity to Contractor of such immediate need prior to performing inspect, such Warranty work. Within seven (7) Days after receiving the notice referenced in the preceding sentence, Contractor shall inspect such *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. work andperformed by Owner and either (i) ratify Owner's work or (ii) elect to repair or otherwise correct Owner's work. In the event that Contractor elects to proceed pursuant to sub-clause (ii), if reasonably practicableContractor shall complete such work, gives Contractor as necessary under the opportunity circumstances, with reasonable promptness. If Owner performs or causes third parties to perform such Warranty work as set forth above, Owner shall provide reasonable access to Contractor to the Facility to observe Owner's and its Affiliates' or any third party's performance of the Warranty work. The performance of Warranty work, either performed by Owner or performed by third parties engaged by Owner which was performed in accordance with the applicable provisions of this Agreement related to such Warranty work that Contractor, had it performed the Warranty work itself, would have observed to comply with this Agreement, shall be deemed covered by the Warranties, and Contractor shall reimburse Owner for all reasonable costs, charges and expenses incurred by Owner in connection therewith plus *** percent (***%).

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)

Failure of Contractor to Perform Warranty Work. If after Substantial Completion, Contractor does not use its reasonable efforts to proceed to complete the applicable Warranty work, or cause any relevant Subcontractor to proceed to complete the Warranty work, required to satisfy any Warranty claim properly asserted under the terms of this Article 1621 in accordance with the terms hereof, Owner shall provide shall, after giving Contractor with a written notice (a “Warranty Claim Notice”) detailing the nature of such Warranty claim, and shall provide Contractor with an opportunity to discuss such claim with Owner (including an opportunity for Contractor to describe why Contractor disagrees with such claim). Within five (5) days after receipt of such Warranty Claim Notice, if Owner is not satisfied that such Warranty claim has been adequately remedied or resolved, or continues to disagree with Contractor regarding such Warranty claim, Owner shall give Contractor a further written notice of Owner’s intent to perform the remedial Warranty work itself or cause at least three (3) Business Days prior to be performed by third partiesOwner’s commencement of any such remedial Warranty work, the work that is the subject of such claim (an “Owner-Performance Notice”). If Contractor fails to commence, or cause any relevant Subcontractor to commence, design, engineering, procurement or other work related to such obligation within five (5) days after its receipt of such Owner-Performance Notice, Owner shall have the right to perform the necessary Warranty work to remedy the Warranty claim, or have third parties perform such the necessary Warranty work and Contractor shall bear the reasonable costs thereof thereof. If Contractor (plus seven percent or the relevant Subcontractor) implements a plan to diligently perform the Warranty work to satisfy such Warranty claim during such three (7%3) Business Day period, and thereafter diligently prosecutes the execution of such costs as an allowance for overhead and related costs); provided that Contractor plan, Owner shall be given the opportunity not perform, or cause any third party to observeperform, review and test the performance of such work and/or the results of such work for the purposes of satisfying itself that such work has been correctly performed in accordance with the Scope of Work and the other applicable provisions of this Agreement related to such work that Contractor, had it performed the work itself, would have observed to comply with this AgreementWarranty work. If any of the Work fails a defect or other nonconformance to satisfy the applicable Warranty arises during the applicable Warranty Period and any such failure defect or nonconformance occurs under circumstances where there is an immediate need for repairs due to the endangerment of human health or property, Owner may Portions of this Exhibit, indicated by the xxxx “[***],” were omitted and have been filed separately with the Securities and Exchange Commission pursuant to the Registrant’s application requesting confidential treatment pursuant to Rule 24b-2 of the Securities Exchange Act of 1934, as amended. perform such Warranty work for Contractor’s account without prior Notice to Contractor; provided that, if practicable, account. If Owner provides reasonably prompt Notice to Contractor of such immediate need prior to performing such Warranty work and, if reasonably practicable, gives Contractor the opportunity performs or causes third parties to perform such Warranty work as set forth above, Owner shall provide reasonable access to Contractor to the Facility to observe Owner’s and its Affiliates’ or any third party’s performance of the Warranty work. The performance of Warranty work, either performed by Owner or performed by third parties engaged by Owner which was performed in accordance with the applicable provisions of this Agreement related to such Warranty work that Contractor, had it performed the Warranty work itself, would have observed to comply with this Agreement, shall be deemed covered by the Warranties, and Contractor shall reimburse Owner for all reasonable costs, charges and expenses incurred by Owner in connection therewith, which shall include a ten percent (10%) mark-up. For clarity, Contractor may not rely upon the failure of any Subcontractor to honor its warranty obligations to excuse or limit Contractor’s Warranties. At Owner’s election, it may apply any Retainage being held under Section 8.1(c) toward any costs for which Contractor is responsible hereunder.

Appears in 1 contract

Samples: Build Transfer Agreement