Common use of Failure of Utility Owners to Cooperate Clause in Contracts

Failure of Utility Owners to Cooperate. ‌ 5.5.7.1 Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Adjustments to be performed pursuant to a Developer Utility Agreement. Developer shall notify IFA immediately if (a) Developer is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Developer Utility Agreement within a reasonable time, (b) Developer reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project or in accordance with Law, the Governmental Approvals or the PPA Documents, (c) Developer becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-upon work or approvals, or (d) any other dispute arises between Developer and a Utility Owner with respect to the Project, despite Xxxxxxxxx's diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such Notice may include a request that IFA assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. Developer shall provide IFA with such information as IFA requests regarding the Utility Owner's failure to cooperate and the effect of any resulting delay on the Project Schedule. After delivering to IFA any Notice or request for assistance, Developer shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.

Appears in 3 contracts

Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement

AutoNDA by SimpleDocs

Failure of Utility Owners to Cooperate. ‌ 5.5.7.1 Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Adjustments to be performed pursuant to a Developer Utility Agreement. Developer shall notify IFA immediately if (a) Developer is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Developer Utility Agreement within a reasonable time, (b) Developer reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project East End Crossing or in accordance with Law, the Governmental Approvals or the PPA Documents, (c) Developer becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-agreed- upon work or approvals, or (d) any other dispute arises between Developer and a Utility Owner with respect to the ProjectEast End Crossing, despite XxxxxxxxxDeveloper's diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such Notice may include a request that IFA assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. Developer shall provide IFA with such information as IFA requests regarding the Utility Owner's failure to cooperate and the effect of any resulting delay on the Project Schedule. After delivering to IFA any Notice or request for assistance, Developer shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.

Appears in 2 contracts

Samples: Public Private Agreement, Public Private Agreement

AutoNDA by SimpleDocs

Failure of Utility Owners to Cooperate. ‌ 5.5.7.1 Developer shall use diligent efforts to obtain the cooperation of each Utility Owner as necessary for Utility Adjustments to be performed pursuant to a Developer Utility Agreement. Developer shall notify IFA immediately if (a) Developer is unable (or anticipates that it will be unable), after diligent efforts, to reach agreement with a Utility Owner on a necessary Developer Utility Agreement within a reasonable time, (b) Developer reasonably believes for any other reason that any Utility Owner would not undertake or permit a Utility Adjustment in a manner consistent with the timely completion of the Project or in accordance with Law, the Governmental Approvals or the PPA Documents, (c) Developer becomes aware that any Utility Owner is not cooperating in a timely manner to provide agreed-agreed- upon work or approvals, or (d) any other dispute arises between Developer and a Utility Owner with respect to the Project, despite XxxxxxxxxDeveloper's diligent efforts to obtain such Utility Owner’s cooperation or otherwise resolve such dispute. Such Notice may include a request that IFA assist in resolving the dispute or in otherwise obtaining the Utility Owner’s timely cooperation. Developer shall provide IFA with such information as IFA requests regarding the Utility Owner's failure to cooperate and the effect of any resulting delay on the Project Schedule. After delivering to IFA any Notice or request for assistance, Developer shall continue to use diligent efforts to pursue the Utility Owner’s cooperation.

Appears in 1 contract

Samples: Public Private Agreement