Failure to Make Good a Deficiency. If the CM/GC does not make good a deficiency within a reasonable space of time fixed in a Notice of Non-Compliant Work, the Owner may do any of the following: Remove the Non-Compliant Work and store it at the expense of the CM/GC. If the CM/GC does not pay the expenses of such removal and storing within ten days after receipt of written demand of the Owner, the Owner may upon three days' notice in writing to the CM/GC sell such materials at private sale or at auction and shall account for the net proceeds thereof after deducting all proper costs incurred by the Owner. Supply omitted work, perform unexecuted work, or replace and re-execute work not done in accordance with the methods and materials designated in the Contract Documents, and deduct the cost thereof from any payment then or thereafter due the CM/GC. The Design Professional shall approve the amount charged to the CM/GC.
Appears in 10 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Failure to Make Good a Deficiency. If the CM/GC does not make good a deficiency within a reasonable space of time fixed in a Notice of Non-Compliant Work, the Owner may do any of the following: :
(a) Remove the Non-Compliant Work and store it at the expense of the CM/GC. If the CM/GC does not pay the expenses of such removal and storing within ten days after receipt of written demand of the Owner, the Owner may upon three days' notice in writing to the CM/GC sell such materials at private sale or at auction and shall account for the net proceeds thereof after deducting all proper costs incurred by the Owner. .
(b) Supply omitted work, perform unexecuted work, or replace and re-execute work not done in accordance with the methods and materials designated in the Contract Documents, and deduct the cost thereof from any payment then or thereafter due the CM/GC. The Design Professional shall approve the amount charged to the CM/GC.
Appears in 6 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Failure to Make Good a Deficiency. If the CM/GC CMR does not make good a deficiency within a reasonable space of time fixed in a Notice of Non-Compliant Work, the Owner Board may do any of the following: :
(a) Remove the Non-Compliant Work and store it at the expense of the CM/GCCMR. If the CM/GC CMR does not pay the expenses of such removal and storing within ten days after receipt of written demand of the OwnerBoard, the Owner Board may upon three days' notice in writing to the CM/GC CMR sell such materials at private sale or at auction and shall account for the net proceeds thereof after deducting all proper costs incurred by the Owner. Board.
(b) Supply omitted work, perform unexecuted work, or replace and re-re- execute work not done in accordance with the methods and materials designated in the Contract Documents, and deduct the cost thereof from any payment then or thereafter due the CM/GCCMR. The Design Professional shall approve the amount charged to the CM/GCCMR.
Appears in 2 contracts
Samples: Construction Management at Risk Agreement, Construction Management at Risk Agreement
Failure to Make Good a Deficiency. If the CM/GC CMR does not make good a deficiency within a reasonable space of time fixed in a Notice of Non-Compliant Work, the Owner Board may do any of the following: :
(a) Remove the Non-Compliant Work and store it at the expense of the CM/GCCMR. If the CM/GC CMR does not pay the expenses of such removal and storing within ten days after receipt of written demand of the OwnerBoard, the Owner Board may upon three days' notice in writing to the CM/GC CMR sell such materials at private sale or at auction and shall account for the net proceeds thereof after deducting all proper costs incurred by the Owner. Board.
(b) Supply omitted work, perform unexecuted work, or replace and re-execute work not done in accordance with the methods and materials designated in the Contract Documents, and deduct the cost thereof from any payment then or thereafter due the CM/GCCMR. The Design Professional shall approve the amount charged to the CM/GCCMR.
Appears in 1 contract