Failure to Remedy; City Action. If the work required to remedy the noticed default or violation is not diligently prosecuted to a completion acceptable to City within the time frame contained in the Notice, City may complete all remaining work, arrange for the completion of all remaining work, and/or conduct such remedial activity as in its sole and absolute discretion it believes is required to remedy the default or violation. All such work or remedial activity shall be at the sole and absolute cost, expense, and liability of Developer and its surety, without the necessity of giving any further notice to Developer or surety. City’s right to take such actions shall in no way be limited by the fact that Developer or its surety may have constructed any, or none of the required or agreed upon Public Improvements at the time of City’s demand for performance. In the event City elects to complete or arrange for completion of the remaining work and improvements, City may require all work by Developer or its surety to cease in order to allow adequate coordination by City. Notwithstanding the foregoing, if conditions precedent for reversion to acreage can be met and if the interests of City will not be prejudiced thereby, City may also process a reversion to acreage and thereafter recover from Developer or its surety the full cost and expense incurred.
AutoNDA by SimpleDocs
Failure to Remedy; City Action. If the work required to remedy the noticed default or violation is not diligently prosecuted to a completion acceptable to CITY within the time frame contained in the Notice, CITY may complete all remaining work, arrange for the completion of all remaining work, and/or conduct such remedial activity as in its sole and absolute discretion it believes is required to remedy the default or violation. All such work or remedial activity shall be at the sole and absolute cost, expense, and liability of Developer and its surety, without the necessity of giving any further notice to Developer or surety. CITY’s right to take such actions shall in no way be limited by the fact that Developer or its surety may have constructed any of the DIF Improvements at the time of CITY’s demand for performance. In the event CITY elects to complete or arrange for completion of the remaining work and the DIF Improvements, CITY may require all work by Developer or its surety to cease in order to allow adequate coordination by CITY.
Failure to Remedy; City Action. If the work required to remedy the noticed default or violation is not diligently prosecuted to a completion acceptable to City within the time frame contained in the Notice, City may complete all remaining work, arrange for the completion of all remaining work, and/or conduct such remedial activity as in its sole and absolute discretion it believes is required to remedy the default or violation. All such work or remedial activity shall be at the sole and absolute cost, expense, and liability of Developer and its surety, without the necessity of giving any further notice to Developer or surety. City’s right to take such actions shall in no way be limited by the fact that Developer or its surety may have constructed any, or none of the required or agreed upon Public Improvements at the time of City’s demand for performance. In the event City elects to complete or arrange for completion of the remaining work and improvements, City may require all work by Developer or its surety to cease in order to allow adequate coordination by City. EXHIBIT “A” Legal Description XxXxxxxx Parking Lot March 31, 2021 BKF No. 20190679 Real property in the City of Milpitas, County of Santa Xxxxx, State of California, and is described as follows: PARCEL ONE: ALL OF PARCEL 3, AS SHOWN UPON THAT CERTAIN PARCEL MAP FILED FOR RECORD IN THE OFFICE OF THE RECORDER OF THE COUNTY OF SANTA XXXXX, STATE OF CALIFORNIA, ON JANUARY 9, 2001 IN BOOK 736 OF MAPS, AT PAGES 10 AND 11 IN THE OFFICE OF THE SANTA CLARA COUNTY RECORDER. PARCEL TWO: ALL OF LOT A, AS SHOWN UPON THAT CERTAIN PARCEL MAP FILED FOR RECORD IN THE OFFICE OF THE RECORDER OF THE COUNTY OF SANTA XXXXX, STATE OF CALIFORNIA, ON JANUARY 9, 2001 IN BOOK 736 OF MAPS, AT PAGES 10 AND 11 IN THE OFFICE OF THE SANTA CLARA COUNTY RECORDER. APN: 000-00-000 This legal description was prepared by me or under my direct supervision in conformance with the requirements of the Professional Land Surveyors Act. BKF Engineers __________________________ Xxxxx Xxxxxxx P.L.S. No. March 31, 2021 Dated BKF 0000 X. Xxxxx Xx, Xxxxx 000, SJ, CA 95112 Exhibit B XxXxxxxx- Parking Lot

Related to Failure to Remedy; City Action

  • Failure to Remedy If the Funder has provided the HSP with an opportunity to remedy the breach, and: the HSP does not remedy the breach within the time period specified in the Notice; it becomes apparent to the Funder that the HSP cannot completely remedy the breach within the time specified in the Notice or such further period of time as the Funder considers reasonable; or the HSP is not proceeding to remedy the breach in a way that is satisfactory to the Funder, then the Funder may immediately terminate this Agreement by giving Notice of termination to the HSP.

  • Remedy for failure to insure If the Concessionaire shall fail to effect and keep in force all insurances for which it is responsible pursuant hereto, the Authority shall have the option to either keep in force any such insurances, and pay such premia and recover the costs thereof from the Concessionaire, or in the event of computation of a Termination Payment, treat an amount equal to the Insurance Cover as deemed to have been received by the Concessionaire.

  • Failure to Respond If you fail to respond by the date given above, your application will be refused under Section 3A(4)(a) of the Registered Designs Act 1949.

  • Failure to Meet Timelines Failure by the Union to comply with the timelines will result in the automatic withdrawal of the grievance. Failure by the Employer to comply with the timelines will entitle the Union to move the grievance to the next step of the procedure.

  • Failure to Meet Time Limits If a grievance is not processed by the grievant in accordance with the time limits set forth in this Article, it shall be considered settled on the basis of the decision last made by the District. If the District fails to respond to the grievance in a timely manner at any level, the running of the time limit shall be deemed a denial of the grievance and termination of the level involved, and the grievant may proceed to the next step.

  • Failure to Vacate If the Resident does not vacate the Residence on the expiry or early termination of this Agreement, (i) the Resident is liable for any financial loss sustained or incurred by the Institution or the Manager, and (ii) the Manager may remove the property of the Resident from the Room (whether or not the Resident is present at the time), and place the property in temporary storage in a location in the Residence of the Manager’s choice, at the Resident’s expense, without notice to the Resident and without liability to the Manager for any damage to or loss of the Resident’s property.

  • Failure to Notify If Contractor fails to specify in writing any problem or circumstance that materially affects the costs of its delivery of services or products, including a material breach by the Department, about which Contractor knew or reasonably should have known with respect to the period during the term covered by Contractor's status report, Contractor shall not be entitled to rely upon such problem or circumstance as a purported justification for an increase in the price for the agreed upon scope.

  • Right to Grieve Disciplinary Action Employees shall have the right to grieve written censures or warnings, and adverse employee appraisals. Employees shall have the right to rebut in writing any disciplinary notice and that rebuttal will be placed in the employee file, but will not be part of the formal disciplinary record. Should an employee dispute any such entry in his/her file, he/she shall be entitled to recourse through the Grievance Procedure and the eventual resolution thereof shall become part of his/her personal record.

  • OUR LIABILITY FOR FAILURE TO STOP PAYMENT If You order Us to place a stop payment on one of Your pre-authorized payments 3 business days or more before the transfer is scheduled, and We do not do so, We will be liable for losses or damages, to the extent provided by law. TRANSACTION SLIPS. Except for mail-in transactions and certain small-value transactions, You can get a receipt at the time You make any transaction to or from Your Account through the use of Your Card. When an electronic fund transfer has been made during any given month, You will receive a monthly statement to reflect all electronic fund transfers to or from Your Account during that statement period. In any case, You will receive a statement at least quarterly. FEES. We may assess reasonable charges against Your Account for transactions performed at electronic terminals. If so, We will specify any charges for these or other types of electronic transactions, including automatic transfers, on an accompanying pricing document. We will explain the charges to You when You open Your Account. You will be provided with a fee schedule, and other specified information after Your Account is established. Additional fee schedules are available at any of Our office locations. When You use an ATM not owned by Us, You may be charged a fee by the ATM operator, or any network used, and You may be charged a fee for a balance inquiry even if You do not complete a fund transfer.