Feasibility Study. 3.3.1 The feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the Small Generating Facility. 3.3.2 A deposit of the good faith estimated feasibility study costs or $5,000, whichever is greater, shall be required from the Interconnection Customer prior to the initiation of the study work. 3.3.3 The scope of and cost responsibilities for the feasibility study are described in the attached feasibility study agreement (Attachment 3). 3.3.4 If the feasibility study shows no potential for adverse system impacts, the Transmission Provider shall send the Interconnection Customer a facilities study agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If no additional facilities are required, the Transmission Provider shall decide whether to send the Interconnection Customer an executable interconnection agreement in accordance with section 3.5.7 of these procedures. 3.3.5 If the feasibility study shows the potential for adverse system impacts, the review process shall proceed to the appropriate system impact study(s).
Appears in 2 contracts
Samples: Standard Small Generator Interconnection Agreement (Sgia), Standard Small Generator Interconnection Agreement (Sgia)
Feasibility Study.
3.3.1 The feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the Small Generating Facility.
3.3.2 A deposit of the lesser of 50 percent of the good faith estimated feasibility study costs or xxxxxxx money of $5,000, whichever is greater, shall 1,000 may be required from the Interconnection Customer prior to the initiation of the study workCustomer.
3.3.3 The scope of and cost responsibilities for the feasibility study are described in the attached feasibility study agreement (Attachment 36).
3.3.4 If the feasibility study shows no potential for adverse system impacts, the Transmission Provider shall send the Interconnection Customer a facilities study agreement, including an outline of the scope of the study and a non-non- binding good faith estimate of the cost to perform the study. If no additional facilities are required, the Transmission Provider shall decide whether to send the Interconnection Customer an executable interconnection agreement in accordance with section 3.5.7 of these procedureswithin five Business Days.
3.3.5 If the feasibility study shows the potential for adverse system impacts, the review process shall proceed to the appropriate system impact study(s).
Appears in 2 contracts
Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Procedures and Agreement
Feasibility Study.
3.3.1 The feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the Small Generating Facility.
3.3.2 A deposit of the good faith estimated feasibility study costs or $5,000, whichever is greater, shall be required from the Interconnection Customer prior to the initiation of the study work.
3.3.3 The scope of and cost responsibilities for the feasibility study are described in the attached feasibility study agreement (Attachment 3).
3.3.4 If the feasibility study shows no potential for adverse system impacts, the Transmission Provider shall send the Interconnection Customer a facilities study agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If no additional facilities are required, the Transmission Provider shall decide whether to send the Interconnection Customer an executable interconnection agreement in accordance with section 3.5.7 of these procedures.
3.3.5 If the feasibility study shows the potential for adverse system impacts, the review process shall proceed to the appropriate system impact study(s).
Appears in 1 contract
Samples: Standard Small Generator Interconnection Agreement (Sgia)
Feasibility Study.
3.3.1 The feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the Small Generating Facility.. Small Generator Interconnection Procedures (SGIP) 11
3.3.2 A deposit of the lesser of 50 percent of the good faith estimated feasibility study costs or xxxxxxx money of $5,000, whichever is greater, shall 1,000 may be required from the Interconnection Customer prior to the initiation of the study workCustomer.
3.3.3 The scope of and cost responsibilities for the feasibility study are described in the attached feasibility study agreement (Attachment 3)agreement.
3.3.4 If the feasibility study shows no potential for adverse system impacts, the Transmission Provider shall send the Interconnection Customer a facilities study agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If no additional facilities are required, the Transmission Provider shall decide whether to send the Interconnection Customer an executable interconnection agreement in accordance with section 3.5.7 of these procedureswithin five Business Days.
3.3.5 If the feasibility study shows the potential for adverse system impacts, the review process shall proceed to the appropriate system impact study(s).
Appears in 1 contract
Samples: Standard Small Generator Interconnection Agreement (Sgia)
Feasibility Study.
3.3.1 The feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the Small Generating Facility.
3.3.2 A deposit of the lesser of 50 percent of the good faith estimated feasibility study costs or xxxxxxx money of $5,000, whichever is greater, shall 1,000 may be required from the Interconnection Customer prior to the initiation of the study workCustomer.
3.3.3 The scope of and cost responsibilities for the feasibility study are described in the attached feasibility study agreement (Attachment 36).
3.3.4 If the feasibility study shows no potential for adverse system impacts, the Transmission Provider shall send the Interconnection Customer a facilities study agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If no additional facilities are required, the Transmission Provider shall decide whether to send the Interconnection Customer an executable interconnection agreement in accordance with section 3.5.7 of these procedureswithin five Business Days.
3.3.5 If the feasibility study shows the potential for adverse system impacts, the review process shall proceed to the appropriate system impact study(s).
Appears in 1 contract