Common use of Feasibility Study Clause in Contracts

Feasibility Study. 4.3.1 The Feasibility Study shall identify any potential adverse system impacts that would result from the interconnection of the Generating Facility. 4.3.2 In order to remain in consideration for interconnection, the Interconnection Customer must return the executed Feasibility Study Agreement within the timeframe agreed upon in the scoping meeting. 4.3.3 A deposit of the good faith estimated Feasibility Study costs may be required from the Interconnection Customer. 4.3.4 The scope of and cost responsibilities for the Feasibility Study are described in the Feasibility Study Agreement. 4.3.5 If the Feasibility Study shows no potential for adverse system impacts, GUC shall send the Interconnection Customer within an agreed upon timeframe a Facilities Study Agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If a Facilities Study is not required, GUC shall send the Interconnection Customer an executable Interconnection Agreement within an agreed upon timeframe. 4.3.6 If the Feasibility Study shows the potential for adverse system impacts, the review process shall proceed to the appropriate System Impact Studies.

Appears in 3 contracts

Samples: Interconnection Procedures, Interconnection Procedures, Interconnection Procedures

AutoNDA by SimpleDocs

Feasibility Study. 4.3.1 The Feasibility Study shall identify any potential adverse system impacts that would result from the interconnection of the Generating Facility. 4.3.2 In order to remain in consideration for interconnection, the Interconnection Customer must return the executed Feasibility Study Agreement within the timeframe agreed upon in the scoping meeting. 4.3.3 A deposit of the good faith estimated Feasibility Study costs may be required from the Interconnection Customer. 4.3.4 The scope of and cost responsibilities for the Feasibility Study are described in the Feasibility Study Agreement. 4.3.5 If the Feasibility Study shows no potential for adverse system impacts, GUC the Utility shall send the Interconnection Customer within an agreed upon timeframe a Facilities Study Agreement, including an outline of the scope of the study and a non-binding good faith estimate of the cost to perform the study. If a Facilities Study is not required, GUC the Utility shall send the Interconnection Customer an executable Interconnection Agreement within an agreed upon timeframe. 4.3.6 If the Feasibility Study shows the potential for adverse system impacts, the review process shall proceed to the appropriate System Impact Studies.

Appears in 2 contracts

Samples: Interconnection Procedures, Interconnection Procedures

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!