Common use of FINAL COMPLETION AND FINAL PAYMENT Clause in Contracts

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 10 contracts

Samples: files.josephlombardo.com, www.fountaininngas.org, Remodeling Agreement

AutoNDA by SimpleDocs

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 15.7.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 15.7.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 6 contracts

Samples: Financial Assistance Grant Agreement, www.gov.bm, www.lickingcountylibrary.org

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 4 contracts

Samples: crdact.net, biznet.ct.gov, Indemnity Agreement

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s on-site visits 's observations and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the said final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section Subparagraph 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 2 contracts

Samples: Agreement (Digex Inc/De), Agreement (Digex Inc/De)

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 14.5.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 Subparagraph 14.5.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 2 contracts

Samples: www.rsfassociation.org, www.dmhprojects.com

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 15.5.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 15.5.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 2 contracts

Samples: themuseumschool.org, www.gov.bm

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 2.9.1 Upon receipt of the ContractorVendor’s notice that the Work is ready for final inspection and acceptance accep xxx xx and upon receipt up on r eceipt of a final Application for Payment, the Architect will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor Vendor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 2.9.2 as precedent to the ContractorVendor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: cms4files1.revize.com

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: agenda.webbcountytx.gov:8085

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Agreement (Sierra Pacific Resources /Nv/)

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment written notice to the Owner, with a copy to the Contractor stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. is due and payable. If the Owner agrees and approves, the Owner will direct the Architect to issue the final Certificate for Payment. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: www.kgbak.us

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section Subparagraph 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Corixa Corp

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 15.7.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect Owner will promptly make such inspection. When the Architect Owner finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect Owner will promptly issue a final Certificate for Payment stating that to the best of the ArchitectOwner’s knowledge, information and belief, and on the basis of the ArchitectOwner’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The ArchitectOwner’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 15.7.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: go.boarddocs.com

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 15.7.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect Architect, and the Manager (if Manager desires) will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 15.7.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: rfp.hawaiiconvention.com

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 14.5.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 Subparagraph 14.5.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Omtool LTD

AutoNDA by SimpleDocs

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 12.5.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed stated in Section 9.10.2 Subparagraph 14.5.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: pine-trk.aspgov.com

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performedhas reached Final Completion, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Agreement

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly prepare, sign, and issue Owner’s Certificate of Final Completion a final Certificate for Payment stating that certifying to the best of the Architect’s knowledge, information and belief, and Owner that on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance with the Contract Documents and that the entire balance balance, including all retainage found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled. Final payments shall be made by the Owner in accordance with Owner’s regular schedule for payments.

Appears in 1 contract

Samples: agenda.webbcountytx.gov:8085

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, belief and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section Subparagraph 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Empire Resorts Inc

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s 's written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, Payment the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s 's on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: STAMPS.COM Inc

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s on-site visits 's observations and inspections, the Work has been completed in accordance with the terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the said final Certificate is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section Subparagraph 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Contract for Construction (Monarch Casino & Resort Inc)

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 Upon receipt of the Contractor’s written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s 's knowledge, information and belief, and on the basis of the Architect’s on-site visits 's observations and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in the said final Certificate for Payment is due and payable. The Architect’s 's final Certificate for Payment will constitute a further representation that conditions listed in Section Subparagraph 9.10.2 as precedent to the Contractor’s 's being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: Construction Contract (National Instruments Corp /De/)

FINAL COMPLETION AND FINAL PAYMENT. § 9.10.1 15.7.1 Upon receipt of the Contractor’s notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such inspection. When inspection and, when the Architect finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect will promptly issue a final Certificate for Payment stating that to the best of the Architect’s knowledge, information and mpleoted furthe a com or wh belief, and on the basis of the Architect’s on-site visits and inspections, the Work has been completed in accordance co with the Contract Documents and that the entire balance found to be due the Contractor and noted in the final n Certificate is due and payable. The Architect’s final Certificate for Payment will constitute a further xxx in accordance in the final r representation that conditions listed stated in Section 9.10.2 15.7.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

Appears in 1 contract

Samples: www.wiltonct.org

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!