Final Completion Milestone Sample Clauses
Final Completion Milestone. Submittals are for review of conformance with the requirements of the Contract. Development of schedules, and schedule updates, and project status reporting requirements of the Contract shall employ computerized Critical Path Method (CPM) scheduling utilizing Microsoft Project. All activities shall have predecessors and successors to generate a project critical path and total float for each activity. Design-Builder must submit a monthly update in Microsoft Project file format along with payment requisition.