Financial Security Arrangements for Small Generating Facilities Processed. Under the Fast Track Process or Small Generating Facilities Processed under SGIP 1. Small Generating Facilities that are no larger than 5 MW that are processed under the Fast Track Process under the Generation Interconnection Procedures, CAISO Tariff Appendix Y; and 2. Small Generating Facilities processed under the Small Generation Interconnection Procedures set forth in CAISO Tariff Appendix S. In such case, the terms of Article 6.4 below do not apply to this Agreement. For easy reference, the Parties shall check the Box below when this Article 6.3 applies:
Appears in 8 contracts
Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Small Generator Interconnection Agreement