Billing, Payment, Milestones, and Financial Security. 6.1 Billing and Payment Procedures and Final Accounting
Billing, Payment, Milestones, and Financial Security. 5.1 Billing and Payment Procedures and Final Accounting (Applies to additional reviews conducted under a Level 2 review and Level 4 reviews)
5.1.1 The EDC shall xxxx the Interconnection Customer for the design, engineering, construction, and procurement costs of EDC provided Interconnection Facilities and Distribution Upgrades contemplated by this Agreement as set forth in Appendix 3, on a monthly basis, or as otherwise agreed by the Parties. The Interconnection Customer shall pay each xxxx within 30 calendar days of receipt, or as otherwise agreed to by the Parties.
5.1.2 Within ninety (90) calendar days of completing the construction and installation of the EDC’s Interconnection Facilities and Distribution Upgrades described in the Attachments 2 and 3 to this Agreement, the EDC shall provide the Interconnection Customer with a final accounting report of any difference between (1) the actual cost incurred to complete the construction and installation and the budget estimate provided to the Interconnection Customer and a written explanation for any significant variation; and (2) the Interconnection Customer’s previous deposit and aggregate payments to the EDC for such Interconnection Facilities and Distribution Upgrades. If the Interconnection Customer’s cost responsibility exceeds its previous deposit and aggregate payments, the EDC shall invoice the Interconnection Customer for the amount due and the Interconnection Customer shall make payment to the EDC within thirty (30) calendar days. If the Interconnection Customer’s previous deposit and aggregate payments exceed its cost responsibility under this Agreement, the EDC shall refund to the Interconnection Customer an amount equal to the difference within thirty (30) calendar days of the final accounting report.
5.1.3 If a Party in good faith disputes any portion of its payment obligation pursuant to this Article 5, such Party shall pay in a timely manner all non-disputed portions of its invoice, and such disputed amount shall be resolved pursuant to the dispute resolution provisions contained in Article 8. Provided such Party’s dispute is in good faith, the disputing Party shall not be considered to be in default of its obligations pursuant to this Article.
Billing, Payment, Milestones, and Financial Security. 6.1 6.1 Billing and Payment Procedures and Final Accounting
6.2 6.2 Milestones 6.3 6.3 Financial Security Arrangements
Billing, Payment, Milestones, and Financial Security. 6.1 Billing and payment procedures and final accounting
6.1.1 The utility shall xxxx the IC for the design, engineering, construction, and procurement costs of attachment facilities and upgrades contemplated by this Agreement on a monthly basis, or as otherwise agreed by the Parties. The IC shall pay each xxxx within 30 calendar days of receipt, or as otherwise agreed to by the Parties.
6.1.2 Within 120 calendar days of completing the construction and installation of the attachment facilities and/or distribution upgrades described in the Attachments to this Agreement, the utility shall provide the IC with a final accounting report of any difference between (i) the IC's cost responsibility for the actual cost of such facilities or upgrades, and (ii) the IC's previous aggregate payments to the utility for such facilities or upgrades. If the IC's cost responsibility exceeds its previous aggregate payments, the utility shall invoice the IC for the amount due and the IC shall make payment to the utility within 30 calendar days. If the IC's previous aggregate payments exceed its cost responsibility under this Agreement, the utility shall refund to the IC an amount equal to the difference within 30 calendar days of the final accounting report.
Billing, Payment, Milestones, and Financial Security. 6.1 Billing and Payment Procedures and Final Accounting
6.1.1 GUC shall bill the Interconnection Customer for the design, engineering, construction, and procurement costs of Interconnection Facilities and Upgrades contemplated by this Agreement in accordance with City (Town) policy (See Appendix 2).
Billing, Payment, Milestones, and Financial Security. 6.1 Billing and Payment Procedures and Final Accounting
6.1.1 The Participating TO shall bill the Interconnection Customer for the design, engineering, construction, and procurement costs of Interconnection Facilities and Upgrades contemplated by this Agreement on a monthly basis, or as otherwise agreed by the Parties. The Interconnection Customer shall pay each bill within thirty (30) calendar days of receipt, or as otherwise agreed to by the Parties. Notwithstanding the foregoing, any invoices between the CAISO and another Party shall be submitted and paid in accordance with the CAISO Tariff.
6.1.2 Within six (6) months of completing the construction and installation of the Participating TO's Interconnection Facilities and/or Upgrades described in the Attachments to this Agreement, the Participating TO shall provide the Interconnection Customer with a final accounting report of any difference between (1) the Interconnection Customer's cost responsibility for the actual cost of such facilities or Upgrades, and (2) the Interconnection Customer's previous aggregate payments to the Participating TO for such facilities or Upgrades. If the Interconnection Customer's cost responsibility exceeds its previous aggregate payments, the Participating TO shall invoice the Interconnection Customer for the amount due and the Interconnection Customer shall make payment to the Participating TO within thirty (30) calendar days. If the Interconnection Customer's previous aggregate payments exceed its cost responsibility under this Agreement, the Participating TO shall refund to the Interconnection Customer an amount equal to the difference within 30 calendar days of the final accounting report.
Billing, Payment, Milestones, and Financial Security. 5.1 Billing and Payment Procedures and Final Accounting
5.1.1 T & D Utility shall xxxx the Interconnection Customer for the design, engineering, construction, and procurement costs of T & D Utility provided Interconnection Facilities and Distribution Upgrades contemplated by this Agreement as set forth in the Exhibits to this Agreement, on a monthly basis, or as otherwise agreed by the Parties. The Interconnection Customer shall pay each xxxx within thirty (30) calendar days of receipt, or as otherwise agreed to by the Parties.
5.1.2 Within ninety (90) calendar days of completing the construction and installation of T & D Utility 's Interconnection Facilities and Distribution Upgrades described in the Exhibits to this Agreement, T & D Utility shall provide the Interconnection Customer with a final accounting report of any difference between (1) the actual cost incurred to complete the construction and installation and the budget estimate provided to the Interconnection Customer and a written explanation for any significant variation. (2) the Interconnection Customer's previous deposit and aggregate payments to T & D Utility for such Interconnection Facilities and Distribution Upgrades. If the Interconnection Customer's cost responsibility exceeds its previous deposit and aggregate payments, T & D Utility shall invoice the Interconnection Customer for the amount due and the Interconnection Customer shall make payment to T & D Utility within thirty (30) calendar days. If the Interconnection Customer's previous deposit and aggregate payments exceed its cost responsibility under this Agreement, T & D Utility shall refund to the Interconnection Customer an amount equal to the difference within thirty (30) calendar days of the final accounting report.
Billing, Payment, Milestones, and Financial Security. 5.1 Billing and Payment Procedures and Final Accounting (Applies to additional reviews conducted under a Level 2 review and Level 4 reviews)
5.1.1 The utility shall bill the interconnection customer for the design, engineering, construction, and procurement costs of utility-provided interconnection facilities and distribution upgrades contemplated by this Agreement as set forth in Attachment 3. An estimate of all anticipated project costs will be provided to the interconnecting customer. The estimated project costs must be paid in full prior to commencing work outlined in Attachment 3. Once project is complete final costs will be assessed, any excess collected funds will be returned to the interconnecting customer, any additional funding will be paid for in full before interconnection is placed in service.
Billing, Payment, Milestones, and Financial Security. Before beginning any work under this Agreement, the Cooperative shall bill the Interconnection Customer for the design, engineering, construction, and procurement costs of Interconnection Facilities and distribution system modifications estimated by the Cooperative to be needed for this interconnection of the Interconnection Customer’s DER. All such fees will be added to the Interconnection Customer’s next monthly bill or presented in an official invoice. In the event that an invoice is provided to the Interconnection Customer, it shall be paid within thirty (30) days of such invoice date.
Billing, Payment, Milestones, and Financial Security. Billing and Payment Procedures and Final Accounting (Applies to additional reviews conducted under a Level 2 review and Level 4 reviews)