FINISHING THE CONTRACT Sample Clauses

FINISHING THE CONTRACT. As built drawings shall be supplied by the contractor by 30 days after the construction completion date. Operating manual shall be supplied by the contractor by [NIL].
AutoNDA by SimpleDocs
FINISHING THE CONTRACT. As built drawings shall be supplied by the contractor by: Fourteen (14) days after Completion Date. Operating manual shall be supplied by the contractor by: Fourteen (14) days after Completion Date.
FINISHING THE CONTRACT. The bidder shall request MP State Food Craft Institute, Rewa to issue a certificate of completion of the Supply, and the MP State Food Craft Institute, Rewa will do so upon deciding the a) Supply of Furniture & Furnishing is as per specification of the Tender b) Installation of Furniture & Furnishing is to the Satisfaction of the Tender Committee / Authorized Person 8.1 Terms of Payment (Annexure - H)
FINISHING THE CONTRACT. 55.1. The Contractor shall request the Engineer to issue a Certificate of Completion of the Works and the Engineer will do so upon deciding that the Work is completed.
FINISHING THE CONTRACT. 53 Completion 53.1 The Contractor shall request the Project Manager to issue a Certificate of Completion of the Works, and the Project Manager shall do so upon deciding that the whole of the Works is completed.
FINISHING THE CONTRACT. Completion 55.1 The Contractor shall request the Employer's Representative to
FINISHING THE CONTRACT. GCC 55.1 Replace the Sub-Clause with the following: The Contractor shall request the Engineer to issue a certificate of Completion of the Works, and the Engineer shall do so upon deciding that the Part-1 Works is completed in all respects.
AutoNDA by SimpleDocs
FINISHING THE CONTRACT. GCC 56.1 * The date by which operating and maintenance manuals are required is within 28 days of issue of certificate of completion of whole or section of work, as the case may be 30.06.2015 GCC 56.2 The amount to be withheld for failing to produce “as built” drawings and/or operating and maintenance manuals *by the date required in G.C.C. 56.1 is Rs.50,000/- GCC 57.2 (g) The maximum number of days is: 90 days GCC 58.1 The percentage to apply to the value of the work not completed, representing the Employer’s additional cost for completing the Works, is 20%.
FINISHING THE CONTRACT. GCC 56.1 * The date by which operating and maintenance manuals are required is within 28 days of issue of certificate of completion of whole or section of work, as the case may be 30.06.2015 * The date by which “as-built” drawings (in scale…) including a compact disc containing digitized drawings in 2 sets are required is within 28 days of issue of certificate of completion of whole or section of the work, as the case may be 30.06.2015.
FINISHING THE CONTRACT. GCC 58.1 The date by which “as-built” drawings (in scale Horizontal 1:2000, Vertical 1:200 in A2 size) in 2 sets are required is within 28 days of issue of certificate of completion of whole or section of the work, as the case may be. [58] GCC 58.2 The amount to be withheld for failing to supply “as built” drawings/ or operating and maintenance manuals by the date required is Rs. 50 Lacs