Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04, then the Firm Operation Date may, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 7 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.06(e) or 3.06(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02Sections 5.02 and 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 4 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.06(e) or 3.06(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02Sections 5.02 and 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 3 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections or 3.06(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02Sections 5.02 and 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure. Notwithstanding the foregoing, the Commercial Operation Deadline shall not be extended beyond the date set forth in Section 1.04(b).
Appears in 3 contracts
Samples: Renewable Power Purchase and Sale Agreement (Montauk Renewables, Inc.), Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04, then the Firm Operation Date may, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.Sections 3.04(c) or 3.04(d),
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.04(d) or 3.04(e), then the Firm Operation Date mayshall, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement (GreenHunter Energy, Inc.)
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections Five.6(e) or Five.6(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02Sections Seven.2 and Seven.5, be extended by Seller on a day-for-day basis for the duration of the Force Majeure. Notwithstanding the foregoing, the Commercial Operation Deadline shall not be extended beyond the date set forth in Section Two.4(b).
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.043.04(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.025.02 and Section 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04, then the Firm Operation Date may, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.Sections 3.04(d) or 3.04(e),
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.04(c) or 3.04(e), then the Firm Operation Date mayshall, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.043.04(c), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.025.02 and Section 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to before the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.06(e) or 3.06(f), then the Firm Operation Date maywill, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.02Sections 5.02 and 5.05, be extended by Seller on a day-for-day day‐for‐day basis for the duration of the Force Majeure.
Appears in 1 contract
Firm Operation Date Extension. If Force Majeure occurs at any time after the commencement of the Facility Term, but prior to the Firm Operation Date, which prevents Seller from demonstrating the Nameplate Contract Capacity as provided in Section 3.04Sections 3.04(d) or 3.04(e), then the Firm Operation Date mayshall, subject to Seller’s compliance with its obligations as the Claiming Party under Section 5.025.02 and to Section 5.05, be extended by Seller on a day-for-day basis for the duration of the Force Majeure.
Appears in 1 contract