Firm Operation Date. The Firm Operation Date shall be the date that is six (6) months after the Initial Operation Date, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.
Appears in 7 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Firm Operation Date. The Firm Operation Date shall be is the date that is six (6) months after the Initial Operation DateOperation, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date. The Firm Operation Date shall be the date that is six twelve (612) months after the Initial Operation Date, plus a day-for-day extension for any additional days for delays due to Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Firm Operation Date. The Firm Operation Date shall be the date that is six three (63) months after the Initial Operation DateOperation, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement (GreenHunter Energy, Inc.)
Firm Operation Date. The Firm Operation Date shall be the date that is six is:
(6a) months Thirty (30) days after the Initial Commercial Operation Date, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed ; or
(b) Agreed to in a writing signed by both Parties.
Appears in 1 contract
Firm Operation Date. The Firm Operation Date shall be the date that is six (6) months after the Initial Operation DateOperation, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.
Appears in 1 contract