FORCE MAJEURE OR EXCUSABLE DELAY Sample Clauses

FORCE MAJEURE OR EXCUSABLE DELAY. Except for a default of Seller’s subcontractor at any tier, Seller shall not be in default or charged for any liability because of a failure to perform the Contract under its terms, or because of a failure to make progress so as to endanger performance, if the failure arises from causes beyond the control of and without the fault of Seller; provided, Seller gives to the Buyer prompt notice in writing as soon as it appears that such cause will delay performance of the Contract. Such causes shall include, without limitation: acts of God or of the public enemy; acts or orders of any Governmental authority, including acts of the Government in its sovereign or contractual capacity; natural disasters including earthquakes, fires, storms, floods, or unusually severe weather; epidemics or quarantine restrictions; unavoidable labor strikes, civil disturbances or acts of terrorism; and freight embargoes. Failure of any relevant government to issue any required import or export license, or withdrawal/termination of a required import or export license by such relevant government, shall relieve Buyer of its obligations under this Contract, and shall relieve Seller of its corresponding obligations. Correspondingly, Company shall not be liable for any failure or delay in performance of the Contract due to causes or circumstances beyond its control and without its fault or negligence.
AutoNDA by SimpleDocs
FORCE MAJEURE OR EXCUSABLE DELAY. Seller shall not be in default or charged for any liability because of a failure to perform the Contract under its terms, or because of a failure to make progress so as to endanger performance, if the failure arises from causes beyond the control of and without the fault of Seller; provided, Seller gives to the Buyer prompt notice in writing as soon as it appears that such cause will delay performance of the Contract. Such causes shall include, without limitation, acts of God, acts or orders of any Governmental authority, natural disasters, unavoidable labor strikes, civil disturbances, acts of terrorism, freight embargoes and unusually severe weather. Correspondingly, the Company shall not be liable for any failure or delay in performance of the Contract due to causes or circumstances beyond its control and without its fault or negligence.
FORCE MAJEURE OR EXCUSABLE DELAY. Supplier shall not be in default or charged for any liability because of a failure to perform the Contract under its terms, or because of a failure to make progress so as to endanger performance, if the failure arises from causes beyond the control of and without the fault of Supplier; provided, Supplier gives to the Buyer prompt notice in writing as soon as it appears that such cause will delay performance of the Contract. Such causes shall include, without limitation, acts of God, acts or orders of any Governmental authority, natural disasters, unavoidable labor strikes, civil disturbances, acts of terrorism, freight embargoes and unusually severe weather. Correspondingly, the Company shall not be liable for any failure or delay in performance of the Contract due to causes or circumstances beyond its control and without its fault or negligence.
FORCE MAJEURE OR EXCUSABLE DELAY. Seller shall not be in default or charged for any liability because of a failure to perform the Contract under its terms, or because of a failure to make progress so as to endanger performance, if the failure arises from causes beyond the control of and without the fault of Seller; provided, Seller gives to Aerojet prompt notice in writing as soon as it appears that such cause will delay performance of the Contract. Such causes shall include, without limitation, acts of God, acts or orders of any Governmental authority, natural disasters, unavoidable labor strikes, civil disturbances, freight embargoes and unusually severe weather. Correspondingly, Aerojet shall not be liable for any failure or delay in performance of the Contract due to causes or circumstances beyond its control and without its fault or negligence.

Related to FORCE MAJEURE OR EXCUSABLE DELAY

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Force Majeure If by reason of Force Majeure, either party hereto shall be rendered unable wholly or in part to carry out its obligations under this Agreement then such party shall give notice and full particulars of Force Majeure in writing to the other party within a reasonable time after occurrence of the event or cause relied upon, and the obligation of the party giving such notice, so far as it is affected by such Force Majeure, shall be suspended during the continuance of the inability then claimed, except as hereinafter provided, but for no longer period, and such party shall endeavor to remove or overcome such inability with all reasonable dispatch. Choice of Law The Agreement between the Vendor and TIPS/ESC Region 8 and any addenda or other additions resulting from this procurement process, however described, shall be governed by, construed and enforced in accordance with the laws of the State of Texas, regardless of any conflict of laws principles. Venue, Jurisdiction and Service of Process Any Proceeding arising out of or relating to this procurement process or any contract issued by TIPS resulting from or any contemplated transaction shall be brought in a court of competent jurisdiction in Camp County, Texas and each of the parties irrevocably submits to the exclusive jurisdiction of said court in any such proceeding, waives any objection it may now or hereafter have to venue or to convenience of forum, agrees that all claims in respect of the Proceeding shall be heard and determined only in any such court, and agrees not to bring any proceeding arising out of or relating to this procurement process or any contract resulting from or any contemplated transaction in any other court. The parties agree that either or both of them may file a copy of this paragraph with any court as written evidence of the knowing, voluntary and freely bargained for agreement between the parties irrevocably to waive any objections to venue or to convenience of forum. Process in any Proceeding referred to in the first sentence of this Section may be served on any party anywhere in the world. Venue for any dispute resolution process, other than litigation, between TIPS and the Vendor shall be located in Camp or Xxxxx County, Texas.

  • FORCE MAJEURE CLAUSE Contractor shall be excused from performance hereunder during the time and to the extent that it is prevented from obtaining delivery, or performing by act of God, fire, strike, loss, or shortage of transportation facilities, lock-out, commandeering of materials, product, plant, or facilities by the government, when satisfactory evidence thereof is presented to the District, provided that it is satisfactorily established that the non-performance is not due to the fault or neglect of Contractor.

  • Force Majeure Event 16.1 If a Force Majeure Event gives rise to a failure or delay in either party performing any obligation under this Agreement (other than any obligation to make a payment), that obligation will be suspended for the duration of the Force Majeure Event.

  • Force Majeure Events a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following: