Further Revisions to Cost Estimate and Project Schedule Sample Clauses

Further Revisions to Cost Estimate and Project Schedule. 6.9.1 If necessary, the A/E shall inform the Contracting Authority and Owner of the need for any adjustments in the Detailed Estimate of Construction Cost and Project Schedule.
AutoNDA by SimpleDocs
Further Revisions to Cost Estimate and Project Schedule. If necessary, the CM shall inform the A/E and the COUNTY of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the COUNTY of any such adjustments, the CM, with the assistance of the A/E, shall prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments, and deliver to the COUNTY.
Further Revisions to Cost Estimate and Project Schedule. If necessary, the Associate shall inform the University of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the University of any such adjustments, the Associate shall prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments, and deliver to the University.
Further Revisions to Cost Estimate and Project Schedule. The Architect and the Construction Manager shall advise the Commission and the School District Board of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the Commission and the School District Board of any such adjustments, the Architect shall assist the Construction Manager in preparing a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments. The Construction Manager shall obtain the School District Board’s signature thereon and deliver the signed, revised Detailed Estimate of Construction Cost or Project Schedule to the Commission.
Further Revisions to Cost Estimate and Project Schedule. If necessary, the Construction Manager shall inform the Agency of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the Agency of any such adjustments, the Construction Manager, with the assistance of the necessary Consultants, shall prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments, and deliver to the Agency.
Further Revisions to Cost Estimate and Project Schedule. If necessary, the Architect/Engineer shall inform the Construction Manager and the City and the YMCA of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule. Upon approval of the City and the YMCA of any such adjustments, the Architect/Engineer shall assist the Construction Manager to prepare a revised Detailed Estimate of Construction Cost or a revised Project Schedule, as applicable, incorporating such adjustments for delivery to the City and the YMCA.
Further Revisions to Cost Estimate and Project Schedule. If Owner has authorized revisions to the Project Budget or Project Schedule to reflect Project bids, Project Manager shall so revise the Project Budget and/or Project Schedule.
AutoNDA by SimpleDocs
Further Revisions to Cost Estimate and Project Schedule. 2.6.9.1 If necessary, the CM shall inform the A/E, the Contracting Authority, and the Owner of the need for any adjustments in the Detailed Estimate of Construction Cost and the Project Schedule.

Related to Further Revisions to Cost Estimate and Project Schedule

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Preliminary Cost Estimates The Engineer shall develop a preliminary cost estimate using the Average Low Bid Unit Price. The Engineer shall estimate the total project cost including preliminary engineering, final engineering, right-of-way (ROW) acquisition, environmental compliance and mitigation, construction, utility relocation, and construction engineering inspection (CEI).