Further Tests. If the work of remedying any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract, including Tests on Completion. The requirement shall be made by notice within 28 days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under sub-clause 11.2 [Cost of Remedying Defects], for the cost of the remedial work.
Appears in 9 contracts
Samples: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract
Further Tests. If the work of remedying any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract, including Tests on Completion. The requirement shall be made by notice within 28 days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under sub-sub- clause 11.2 [Cost of Remedying Defects], for the cost of the remedial work.
Appears in 4 contracts
Samples: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract
Further Tests. If the work of remedying any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract, including Tests on Completion and/or Tests after Completion. The requirement shall be made by notice within 28 days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under sub-clause 11.2 [Cost of Remedying Defects], for the cost of the remedial work.
Appears in 2 contracts
Samples: Contractor Agreement, Contractor Agreement
Further Tests. If the work of remedying of any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract, including Tests on Completion. The requirement shall be made by notice within 28 days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under subSub-clause 11.2 [Cost of Remedying Defects], for the cost of the remedial work.Clause
Appears in 1 contract
Samples: Unit Price Contract
Further Tests. If the work of remedying of any defect or damage may affect the performance of the Works, the Engineer Project Manager may require the repetition of any of the tests described in the Contract, including Tests on Completion. The requirement shall be made by notice within 28 14 working days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under sub-clause GCC 11.2 [Cost of Remedying Defects], for the cost of the remedial work.
Appears in 1 contract
Samples: Contract for Design and Construction
Further Tests. If the work of remedying of any defect or damage may affect the performance of the Works, the Engineer may require the repetition of any of the tests described in the Contract, including Tests on Completion. The requirement shall be made by notice within 28 days after the defect or damage is remedied. These tests shall be carried out in accordance with the terms applicable to the previous tests, except that they shall be carried out at the risk and cost of the Party liable, under subSub-clause Clause 11.2 [Cost of Remedying Defects], for the cost of the remedial work.
Appears in 1 contract
Samples: Unit Price Contract