Giving of Relief. In the event that the Contractor has complied with its obligations under Clause 15.6 above, then: 15.7.1 the Relevant Date shall be postponed by such time as shall be reasonable for such a Compensation Event, taking into account the likely effect of delay; 15.7.2 in the case of an additional cost being incurred or revenue being lost by the Contractor: (a) on or before the Relevant Date; or (b) as a result of Capital Expenditure being incurred by the Contractor at any time, the Authority shall compensate the Contractor for the actual Estimated Change in Project Costs as adjusted to reflect the actual costs reasonably incurred and without double counting, for revenue actually lost (to the extent it could not reasonably have been negotiated) within twenty (20) Working Days of its receipt of a written demand by the Contractor supported by all relevant information; 15.7.3 in the case of a payment of compensation for the Estimated Change in Project Costs and/or without double counting loss of revenue that does not result in Capital Expenditure being incurred by the Contractor referred to in Clause 15.7.2(b) above but which reflects a change in the costs being incurred by the Contractor after the Relevant Date, the Authority shall compensate the Contractor in accordance with Clause 15.11 (Payment) below by an adjustment to the Unitary Charge; and/or; 15.7.4 the Authority shall give the Contractor such relief from its obligations under the Contract, as is reasonable for such a Compensation Event.
Appears in 3 contracts
Samples: Agreement for Islington Hra Pfi Street Properties, Agreement for Islington Hra Pfi Street Properties, Agreement for Islington Hra Pfi Street Properties
Giving of Relief. In the event that the Contractor has complied with its obligations under Clause clause 15.6 above(Procedure for Relief), then:then:-
15.7.1 in the Relevant case of delay, the Start on Site Date; and/or the relevant Target Practical Completion Date, Target Service Availability Date or, following the Target Service Availability Date, the relevant Longstop Date shall be postponed by such time as shall be reasonable for such a Compensation Event, taking into account the likely effect of delay;
15.7.2 in the case of an any additional cost being incurred or revenue being lost by the Contractor:Contractor:-
(a) in relation to a New Facility on or before the Relevant Target Service Availability Date; or
(b) as a result of Capital Expenditure being incurred by the Contractor at any time, ; the Authority shall compensate the Contractor for the actual Estimated Change in Project Costs as adjusted to reflect the actual costs reasonably Estimated Change in Project Costs incurred and and, without double counting, for revenue actually lost (to the extent it could would not reasonably have been negotiated) mitigated), within twenty thirty (2030) Working Days of its receipt of a written demand by the Contractor supported by all relevant information;
15.7.3 in the case of a payment of compensation for the Estimated Change in Project Costs and/or and/or, without double counting counting, loss of revenue that does not result in Capital Expenditure being incurred by the Contractor referred to in Clause 15.7.2(b) above but which reflects a change in the costs being incurred by the Contractor after the Relevant Date, clause 15.7.2 the Authority shall compensate the Contractor for the actual Estimated Change in accordance with Clause 15.11 Project Costs incurred (Paymentto the extent that it could not reasonably have been mitigated) below by an adjustment to the Annual Unitary ChargeCharge in accordance with clause 27.3; and/or;
15.7.4 the Authority shall give the Contractor such relief from its obligations under the Contract, this Agreement as is reasonable for such a Compensation Event.
Appears in 1 contract
Samples: Project Agreement