Extensions of Time Sample Clauses

Extensions of Time. 34.1 If at any time during performance of the Contract, the Supplier or its subcontractors should encounter conditions impeding timely delivery of the Goods or completion of Related Services pursuant to GCC Clause 13, the Supplier shall promptly notify the Procuring Entity in writing of the delay, its likely duration, and its cause. As soon as practicable after receipt of the Supplier's notice, the Procuring Entity shall evaluate the situation and may at its discretion extend the Supplier's time for performance, in which case the extension shall be ratified by the parties by amendment of the Contract. 34.2 Except in case of Force Majeure, as provided under GCC Clause 32, a delay by the Supplier in the performance of its Delivery and Completion obligations shall render the Supplier liable to the imposition of liquidated damages pursuant to GCC Clause 26, unless an extension of time is agreed upon, pursuant to GCC Sub-Clause 34.1.
AutoNDA by SimpleDocs
Extensions of Time. The Parties reserve the right, by agreement and subject to the Court’s approval, to grant any reasonable extension of time that might be needed to carry out any of the provisions of this Agreement.
Extensions of Time. 4.5.1 In the event that the SPD is prevented from performing its obligations under Article 4.1 by the SCSD due to: a) any SECI Event of Default; or b) Force Majeure Events affecting SECI/ Buying Entity(ies) , or c) Force Majeure Events affecting the SPD, the SCSD and the Expiry Date shall be deferred, for a reasonable period but not less than ‘day for day’ basis, to permit the SPD or SECI/ Buying Entity(ies) through the use of due diligence, to overcome the effects of the Force Majeure Events affecting the SPD or SECI/Buying Entity(ies), or till such time such Event of Default is rectified by SECI. 4.5.2 Subsequent to grant of connectivity, in case there is a delay in operationalization of GNA by the CTU and/or there is a delay in readiness of the ISTS substation at the Delivery Point, including readiness of the power evacuation and transmission infrastructure of the ISTS network until SCSD of the Project, and it is established that: (i) The SPD has complied with the complete application formalities as per RfS, (ii) The SPD has adhered to the applicable Procedure in this regard as notified by the CERC/CTU, and (iii) The delay in operationalization of GNA and/or delay in readiness of the ISTS substation at the Delivery Point, including readiness of the power evacuation and transmission infrastructure of the ISTS network, is solely attributable to the CTU/transmission licensee and is beyond the control of the SPD; The above shall be treated as delays beyond the control of the SPD and SCSD for such Projects shall be revised as the date as on 60 days subsequent to the readiness of the Delivery Point and power evacuation infrastructure and/or grant/operationalization of GNA. Decision on requisite extension on account of the above factor shall be taken by SECI. In case of change in Project location(s) by the SPD, extension requests under this Article shall be dealt by SECI on case-to-case basis. For avoidance of ambiguity, it is clarified that for decisions made under this Article, the phrase “change in Project location” or its similar connotations, shall refer solely to change in Delivery Point(s) of the Project. 4.5.3 In case of extension due to reasons specified in Article 4.5.1(b) and (c), and if such Force Majeure Event continues even after a maximum period of nine (9) months from the date of the Force Majeure Notice, termination of this Agreement shall be caused solely at the discretion of SECI, as per the provisions of Article 13.5. 4.5.4 If the Parties h...
Extensions of Time. The Settling Parties may agree upon a reasonable extension of time for deadlines and dates reflected in this Settlement Agreement, without further notice (subject to Court approval as to Court dates).
Extensions of Time. Applications for extensions of time shall be made on the Teton County “Development Agreement Extension Application” attached hereto as Exhibit D and shall address the criteria presented on that form. The Developer shall pay the fee associated with the request. Developer acknowledges and agrees the Board of County Commissioners has the sole discretion to grant or deny a request for extension. Any application for an extension of time must be submitted to the Planning Department before the expiration of the original deadline.
Extensions of Time. The Developer may be allowed extensions of time for commencement of construction, or for beyond the completion date, for unavoidable delays such as those caused by strikes, lockouts, acts of God, or factors beyond the control of the Developer. Application for extension shall be made on the Teton County “Development Agreement Extension Application” and shall address the criteria presented on that form and in Exhibit C, Extension Criteria. The Developer shall pay the fee associated with the request. Developer acknowledges and agrees that the Board of County Commissioners has the sole discretion to grant or deny a request for extension. The application for a development agreement extension must be submitted to the Planning Department before the expiration of the original development agreement.
Extensions of Time. 5.7.1 In the event that the Developer is prevented from performing its obligations under Clause 5.1 by the Scheduled Commissioning Date due to: a) any ESCOM Event of Defau lt; or b) Force Majeure Events affecting ESCOM; or c) Force Majeure Events affecting the Developer, the Scheduled Commissioning Date and the Expiry Date shall be deferred, subject to the limit prescribed in Clause 5.7.2 and Clause 5.7.3 for a reasonable period but not less than ‘day for day’ basis, to permit the Developer or ESCOM through the use of due diligence, to overcome the effects of the Force Majeure Events affecting the Developer or ESCOM, or till such time such Event of Default is rectified by ESCOM. 5.7.2 In case of extension occurring due to reasons specified in clause 5.7.1(a), any of the dates specified therein can be extended, subject to the condition that the Scheduled Commissioning Date would not be extended by more than 6(six) months. 5.7.3 In case of extension due to reasons specified in Article 5.7.1(b) and (c), and if such Force Majeure Event continues even after a maximum period of 3(three) months, any of the Parties may choose to terminate the Agreement as per the provisions of Article 16. If the Parties have not agreed, within 30 (thirty) days after the affected Party’s performance has ceased to be affected by the relevant circumstance, on the time period by which the Scheduled Commissioning Date or the Expiry Date should be deferred by, any Party may raise the Dispute to be resolved in accordance with Article18. 5.7.4 As a result of such extension, the Scheduled Commissioning Date and the Expiry Date newly determined shall be deemed to be the Scheduled Commissioning Date and the Expiry Date for the purposes of this Agreement.
AutoNDA by SimpleDocs
Extensions of Time. 4.7.1 In the event that the SPP is prevented from performing its obligations under Article 4.1 by the Scheduled Commissioning Date due to: a) any STU/Procurers Event of Default; or b) Force Majeure Events affecting STU/Procurers, or c) Force Majeure Events affecting the SPP, the Scheduled Commissioning Date and the Expiry Date shall be deferred, subject to the limit prescribed in Article 4.7.2, for a reasonable period but not less than „day for day‟ basis, to permit the SPP or STU/Procurers through the use of due diligence, to overcome the effects of the Force Majeure Events affecting the SPP or Procurers, or till such time such Event of Default is rectified by STU/Procurers. 4.7.2 Subject to Article 4.7.6, in case of extension occurring due to reasons specified in Article 4.7.1(a), any of the dates specified therein can be extended, subject to the condition that the Scheduled Commissioning Date would not be extended by more than six (6) Months. 4.7.3 In case of extension due to reasons specified in Article 4.7.1(b) and (c), and if such Force Majeure Event continues even after a maximum period of three (3) months any of the Parties may choose to terminate the Agreement as per the provisions of Article 13.5. 4.7.4 If the Parties have not agreed, within thirty (30) days after the affected Party‟s performance has ceased to be affected by the relevant circumstance, on the time period by which the Scheduled Commissioning Date or the Expiry Date should be deferred by, any Party may raise the Dispute to be resolved in accordance with Article 16. 4.7.5 As a result of such extension, the Scheduled Commissioning Date and the Expiry Date newly determined shall be deemed to be the Scheduled Commissioning Date and the Expiry Date for the purposes of this Agreement. 4.7.6 Notwithstanding anything to the contrary contained in this Agreement, any extension of the Scheduled Commissioning Date arising due to any reason envisaged in this Agreement shall not be allowed beyond 6 months or date determined pursuant to Article 4.7.1 whichever is later.
Extensions of Time. Unless otherwise ordered by the Court, the Parties may agree to reasonable extensions of time to carry out any of the terms of this Agreement and Settlement.
Extensions of Time. The time limitations specified for either the grievant or the College may be extended by written mutual agreement. Such extension of time on the part of the College Area must be approved by the Director of Labor Relations/General Counsel, or his designee, for STEPS ONE through THREE.