GMP Exhibit. The GMP Exhibit shall include the following, unless the parties mutually agree otherwise: 6.6.2.1.1 The GMP, which shall be the sum of: i. Design-Builder’s Fee as defined in Section 6.2.1 hereof; ii. The estimated Cost of the Work as defined in Section 6.3 hereof, inclusive of any Design-Builder’s Contingency as defined in Section 6.6.1.2 hereof; and 6.6.2.1.2 The Basis of Design Documents, which may include, by way of example, Owner’s Project Criteria, which are set forth in detail and are attached to the GMP Exhibit; 6.6.2.1.3 A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Exhibit, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents; 6.6.2.1.4 The Scheduled Substantial Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 5.2.1 hereof, and a schedule upon which the Scheduled Substantial Completion Date is based; 6.6.2.1.5 If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis; 6.6.2.1.6 If applicable, a schedule of alternate prices; 6.6.2.1.7 If applicable, a schedule of unit prices; and 6.6.2.1.8 If applicable, a statement of Additional Services which may be performed but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Contract Time(s).
Appears in 8 contracts
Samples: Agreement Between Owner and Design Builder Cost Plus Fee With a Guaranteed Maximum Price, Design Build Agreement, Design Build Agreement
GMP Exhibit. The GMP Exhibit shall include the following, unless the parties mutually agree otherwise:
6.6.2.1.1 The GMP, which shall be the sum of:
i. Design-Builder’s Fee as defined in Section 6.2.1 hereof;
ii. The estimated Cost of the Work as defined in Section 6.3 hereof, inclusive of any Design-Builder’s Contingency as defined in Section 6.6.1.2 hereof; andSection
6.6.2.1.2 The Basis of Design Documents, which may include, by way of example, Owner’s Project Criteria, which are set forth in detail and are attached to the GMP Exhibit;
6.6.2.1.3 A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Exhibit, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents;
6.6.2.1.4 The Scheduled Substantial Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 5.2.1 hereof, and a schedule upon which the Scheduled Substantial Completion Date is based;
6.6.2.1.5 If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis;
6.6.2.1.6 If applicable, a schedule of alternate prices;
6.6.2.1.7 If applicable, a schedule of unit prices; and
6.6.2.1.8 If applicable, a statement of Additional Services which may be performed but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Contract Time(s).
Appears in 1 contract
Samples: Agreement Between Owner and Design Builder Cost Plus Fee With a Guaranteed Maximum Price
GMP Exhibit. The GMP Exhibit shall include the following, unless the parties mutually agree otherwise:
6.6.2.1.1 The GMP, which shall be the sum of:
i. Design-Builder’s Fee as defined in Section 6.2.1 hereof;
ii. The estimated Cost of the Work as defined in Section 6.3 hereof, inclusive of any Design-Builder’s Contingency as defined in Section 6.6.1.2 hereof; and
6.6.2.1.2 The Basis of Design Documents, which may include, by way of example, Owner’s Project Criteria, which are set forth in detail and are attached to the GMP Exhibit;
6.6.2.1.3 A list of the assumptions and clarifications made by Design-Builder in the preparation of the GMP Exhibit, which list is intended to supplement the information contained in the drawings and specifications and is specifically included as part of the Basis of Design Documents;
6.6.2.1.4 The Scheduled Substantial Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 5.2.1 hereof, and a schedule upon which the Scheduled Substantial Completion Date is based;
6.6.2.1.5 The updated Procurement and Equity Plan;
6.6.2.1.6 If applicable, a list of Allowance Items, Allowance Values, and a statement of their basis;
6.6.2.1.6 6.6.2.1.7 If applicable, a schedule of alternate prices;
6.6.2.1.7 6.6.2.1.8 If applicable, a schedule of unit prices; and
6.6.2.1.8 6.6.2.1.9 If applicable, a statement of Additional Services which may be performed but which are not included in the GMP and which, if performed, shall be the basis for an increase in the GMP and/or Contract Time(s).