GMP Proposal. A GMP Proposal to Owner shall include the following, unless the parties mutually agree otherwise: i. A proposed GMP; ii. A list of the Drawings and Specifications, including all addenda, used as the basis for the GMP proposal; iii. A list of the assumptions and clarifications made by CM/GC in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the Drawings and Specifications; iv. The Scheduled Final Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 2.b.xx hereof, and a schedule upon which the Scheduled Financial Completion Date is based; v. If applicable, a list of allowances and a statement of their basis and a statement that, to the best of CM/GC’s knowledge, the cost pertaining to such allowance item is a reasonable estimate taking into account (i) the Project plans and other Contract Documents existing at the time the allowance estimate is made; (ii) the labor and material standards and construction means, methods and techniques prevailing in the industry for projects similar to the Project; and (iii) the level of labor and material costs generally prevailing in the locality of the Project at the time the allowance estimate is made.
Appears in 3 contracts
Samples: Construction Management/General Contractor Agreement, Construction Management/General Contractor Agreement, Construction Management/General Contractor Agreement
GMP Proposal. A GMP Proposal to Owner shall include the following, unless the parties mutually agree otherwise:
i. 6.7.4.1 A proposed GMP;
ii. 6.7.4.2 A list of the Drawings and Specifications, including all addenda, used as the basis for the GMP proposal;
iii. 6.7.4.3 A list of the assumptions and clarifications made by CMDesign/GC Builder in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the Drawings drawings and Specificationsspecifications;
iv. 6.7.4.4 The Scheduled Final Substantial Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 2.b.xx Article 5 hereof, and a schedule upon which the Scheduled Financial Substantial Completion Date is based;
v. 6.7.4.5 If applicable, a list of allowances and a statement of their basis and a statement that, to the best of CMDesign/GCBuilder’s knowledge, the cost pertaining to such allowance item is a reasonable estimate taking into account (i) the Project plans and other Contract Documents existing at the time the allowance estimate is made; (ii) the labor and material standards and construction means, methods and techniques prevailing in the industry for projects similar to the Project; and (iii) the level of labor and material costs generally prevailing in the locality of the Project at the time the allowance estimate is made;
6.7.4.6 If applicable, a schedule of alternate prices;
6.7.4.7 If applicable, a schedule of unit prices;
6.7.4.8 If applicable, a statement of Additional Services; and
6.7.4.9 The time limit for acceptance of the GMP Proposal.
Appears in 1 contract
Samples: Design/Build Agreement
GMP Proposal. A GMP Proposal to Owner shall include the following, unless the parties mutually agree otherwise:
i. 6.4.1 A proposed GMP;
ii. 6.4.2 A list of the Drawings and Specifications, including all addenda, used as the basis for the GMP proposal;
iii. 6.4.3 A list of the assumptions and clarifications made by CM/GC in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the Drawings and Specifications;
iv. 6.4.4 The Scheduled Final Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 2.b.xx 2.1.2.20 hereof, and a schedule upon which the Scheduled Financial Completion Date is based;
v. 6.4.5 If applicable, a list of allowances and a statement of their basis and a statement that, to the best of CM/GC’s knowledge, the cost pertaining to such allowance item is a reasonable estimate taking into account (i) the Project plans and other Contract Documents existing at the time the allowance estimate is made; (ii) the labor and material standards and construction means, methods and techniques prevailing in the industry for projects similar to the Project; and (iii) the level of labor and material costs generally prevailing in the locality of the Project at the time the allowance estimate is made.;
Appears in 1 contract
Samples: Construction Management/General Contractor Agreement
GMP Proposal. A GMP Proposal to Owner shall include the following, unless the parties mutually agree otherwise:
i. 6.07.04.01 A proposed GMP;
ii. 6.07.04.02 A list of the Drawings and Specifications, including all addenda, used as the basis for the GMP proposal;
iii. 6.07.04.03 A list of the assumptions and clarifications made by CMDesign/GC Builder in the preparation of the GMP Proposal, which list is intended to supplement the information contained in the Drawings drawings and Specificationsspecifications;
iv. 6.07.04.04 The Scheduled Final Completion Date upon which the proposed GMP is based, to the extent said date has not already been established under Section 2.b.xx Article 5 hereof, and a schedule upon which the Scheduled Financial Final Completion Date is based;
v. 6.07.04.05 If applicable, a list of allowances and a statement of their basis and a statement that, to the best of CMDesign/GCBuilder’s knowledge, the cost pertaining to such allowance item is a reasonable estimate taking into account (i) the Project plans and other Contract Documents existing at the time the allowance estimate is made; (ii) the labor and material standards and construction means, methods and techniques prevailing in the industry for projects similar to the Project; and (iii) the level of labor and material costs generally prevailing in the locality of the Project at the time the allowance estimate is made;
6.07.04.06 If applicable, a schedule of alternate prices;
6.07.04.07 If applicable, a schedule of unit prices;
6.07.04.08 If applicable, a statement of Additional Services; and
6.07.04.09 The time limit for acceptance of the GMP Proposal.