Government response. The Contracting Officer shall promptly, within to be inserted at task order level calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either-- (1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; (2) Countermand any communication regarded as a change; (3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or (4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 16 contracts
Government response. The Contracting Officer shall promptly, within to be inserted at task order level calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 14 contracts
Samples: Contract, Solicitation, Offer and Award, Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 7 contracts
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 15 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 6 contracts
Samples: Contract, Solicitation, Offer and Award, Solicitation, Offer and Award
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 14 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 6 contracts
Samples: Purchase Order, Purchase Order, Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 10 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 4 contracts
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 3 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 3 contracts
Samples: Contract, Solicitation, Offer and Award, Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level three (3) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 3 contracts
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 45 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Samples: Solicitation, Offer and Award, Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either —
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's ’s notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Samples: Contract (Viasat Inc), Contract (Viasat Inc)
Government response. The Contracting Officer shall promptly, within calendar days (to be inserted at task order level calendar days after negotiated) of receipt of notice, respond to the notice in writing. In responding, the The Contracting Officer shall either--either-
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary necessary, direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Samples: Contract (Markland Technologies Inc), Contract (Technest Holdings Inc)
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 5 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Samples: Contract, Solicitation, Offer and Award
Government response. The Contracting Officer shall promptly, within to be inserted at task order level twenty-one (21) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either --
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 2 contracts
Samples: Purchase Order, Purchase Order
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 7 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either —
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's Contractors notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level FIVE (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either –
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand Counter any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's Contractors notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Purchase Order
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 7 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either --
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct necessarydirect the mode of further performance;
; (2) Countermand any communication anycommunication regarded as a change;
; (3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct necessarydirect the mode of further performance; or
or (4) In the event the Contractor's ’s notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level THIRTY calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Government response. The Contracting Officer shall promptly, within _____ calendar days (to be inserted at task order level calendar days after negotiated) of receipt of notice, respond to the notice in writing. In responding, the The Contracting Officer shall either--either-
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary necessary, direct the mode of further performance; or
(4) In the event the Contractor's ’s notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 30 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either—
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's ’s notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract (Trius Therapeutics Inc)
Government response. The Contracting Officer shall promptly, within [ ] (to be inserted at task order level negotiated) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either-
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level TBD calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 21 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 15 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either --
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's ’s notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract Clauses
Government response. The Contracting Officer shall promptly, within to be inserted at task order level TBD calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either --
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's Contractors notice information is inadequate to make a decision under subparagraphs (1d)(1), (2), or (3) aboveof this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 1 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract
Government response. The Contracting Officer shall promptly, within to be inserted at task order level 45 calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either--either—
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor's ’s notice information is inadequate to make a decision under (1), (2), or (3) above, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
Appears in 1 contract
Samples: Contract (Beacon Power Corp)