Hazardous Material Safety Precautions And Programs. 10.15.1.4.1 In the event that either the Owner or the Contractor become aware that an area in which the work will be performed is contaminated with asbestos containing material or polychlorinated biphenyl (PCB) that party shall promptly notify the other party of the existence of the contamination and the work shall be suspended until the contamination has been removed. It shall be the Owner's responsibility to decontaminate any area where asbestos containing material or PCB levels exceed acceptable legal limits. Owner further agrees that it has established an asbestos contamination monitoring and maintenance program. 10.15.1.4.2 The Contractor by signing this Agreement, certifies that no asbestos or asbestos containing materials will be installed or used in this project in order to satisfy Federal Register, Part III, Environmental Protection Agency 40 CRF, Part 763.85 Asbestos Containing Materials in Schools; Final Rule Notice. 10.15.1.4.3 The Contractor by signing this agreement certifies and agrees that no lead or lead containing materials will be installed or used on this project. 10.15.1.4.4 Each Subcontractor shall be responsible and pay for any damage that the Subcontractor may do to the property or work of others.
Appears in 11 contracts
Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services
Hazardous Material Safety Precautions And Programs. 10.15.1.4.1 In the event that either the Owner owner or the Contractor contractor become aware that an area in which the work will be performed is contaminated with asbestos containing material or polychlorinated biphenyl (PCB) that party shall promptly notify the other party of the existence of the contamination and the work shall be suspended until the contamination has been removed. It shall be the Ownerowner's responsibility to decontaminate any area where asbestos containing material or PCB levels exceed acceptable legal limits. Owner further agrees that it has established an asbestos contamination monitoring and maintenance program.
10.15.1.4.2 The Contractor contractor by signing this Agreement, certifies that no asbestos or asbestos containing materials will be installed or used in this project in order to satisfy Federal Register, Part III, Environmental Protection Agency 40 CRF, Part 763.85 Asbestos Containing Materials in Schools; Final Rule Notice.
10.15.1.4.3 The Contractor contractor by signing this agreement certifies and agrees that no lead or lead containing materials will be installed or used on this project.
10.15.1.4.4 Each Subcontractor subcontractor shall be responsible and pay for any damage that the Subcontractor subcontractor may do to the property or work of others.
Appears in 3 contracts
Samples: Construction Agreement, Construction Agreement, Construction Agreement