Common use of Impediments and Delays Clause in Contracts

Impediments and Delays. If timely performance of the Services is affected due to impediments or delays caused by the Company or any third parties engaged by the Company: the Contractor shall promptly notify the Company of the circumstances and probable effects of such impediment or delay on the performance of the Services (if not notified in timely manner, the Contractor shall lose its right to make any claim in this respect); and the Parties shall in good faith discuss such allegation of the Contractor, and, if agreed, the duration of the Services (including the term for delivery of any pending Services) shall be extended by the number of days directly affected by such impediment or delay.

Appears in 10 contracts

Samples: Framework Agreement, Framework Agreement, Framework Agreement