Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. 4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD. 4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD. 4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation. 4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his its own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU STU/ CTU as under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Not Used.
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU SPIA shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Government of India from time to time issues order for waiver of inter-state transmission system (ISTS) charges and losses on transmission of wind/solar power till a certain date. In case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver, arising out of any reasons whatsoever, SECI shall bear no liability with respect to transmission charges and losses levied, if any.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ CTU / concerned authority with regard to the ISTS connected Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the interconnection /Metering/Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to interconnection /Metering/Delivery point, will entirely be of the SPD, at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the interconnection /Metering/Delivery point shall also be the responsibility of the SPD.
4.2.2 4.2.3 The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the interconnection /Metering/Delivery Point shall be borne by the SPD and the same will not be reimbursed by NTPC or met by any other entity to whom this solar power is sold by NTPC. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection interconnection /Metering/Delivery Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement 4.2.7 At least 30 days before proposed commissioning date, the SPD shall be required to submit the connectivity letter from Central Transmission Utility (CTU), confirming technical feasibility of connectivity of the plant to the CTU substation. Copy of Long Term Access (LTA) agreement shall also be made submitted by the SPD through a dedicated transmission line. The entire cost one month prior to commissioning of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPDProject. In case of any delay in the project developer is unable to obtain connectivity to and/or LTA at least one month before proposed commissioning date for the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.and it is established that the SPD has complied with the complete application formalities as per Clause
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all necessary information from the STU/ CTU/ NTPC/CTU / concerned authority with regard to the Interconnection Facilities as is reasonably necessary interconnection at existing NTPC switchyard in Western Region to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the interconnection /Metering/Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to interconnection /Metering/Delivery point, will entirely be of the SPD, at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the interconnection /Metering/Delivery point shall be the responsibility of the SPD.
4.2.2 4.2.3 The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the interconnection /Metering/Delivery Point shall be borne by the SPD and the same will not be reimbursed by NTPC or met by the Discom(s). In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection interconnection /Metering/Delivery Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement 4.2.7 At least 30 days before proposed commissioning date or Scheduled Commissioning Date as the case may be, the project developer shall be required to submit the connectivity letter from Central Transmission Utility (CTU), confirming technical feasibility of connectivity of the plant to the NTPC/CTU substation. Copy of Long Term Access (LTA) agreement shall also be made submitted by the SPD through a dedicated transmission line. The entire cost project developer one month prior to commissioning of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPDProject. In case of any delay in the project developer is unable to obtain connectivity to and/or LTA at least one month before proposed commissioning date or Scheduled Commissioning Date as the Project and non- availability of Grid and Transmission System during Term of this Agreement, case may be for the reasons not attributable to the SPD, provisions of Article 4.9 shall and it is established that the project developer has complied with the complete application formalities as per Clause 3.1 h), and has adhered to the applicable Procedure in this regard as notified by the CERC/CTU, the Scheduled Commissioning Date for the Project may be applicable.extended for a period upto Twelve
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ SPIA/STU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s SPD‟s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection PointPoint as per the SPIA terms and conditions, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU SPIA shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.[Not Used]
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission lineline as instructed by the SPIA. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 14 shall be applicable.
4.2.6 Interconnection Delivery point will be at the Grid substation and therefore from Generators substation/switchyard transmission line will be in scope of SPIA. The maintenance of Transmission system up to the Inter-connection Point shall be adhered to as per the Terms and Conditions of SPIA.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Government of India, from time to time, issues order for waiver of inter-state transmission system (ISTS) charges and losses on transmission of solar power till a certain date. In case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver, arising out of any reasons whatsoever, SECI shall bear no liability with respect to transmission charges and losses levied, if any. However, in case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver/extended SCD as above, due to reasons attributable to the SPD, the liability of transmission charges and losses would be to the account of the SPD. Delay in Project commissioning beyond the deadline as stipulated by the Government of India, and treatment of ISTS charges and losses thereof, shall be dealt in line with the Central Electricity Regulatory Commission (Sharing of Inter- State Transmission Charges and Losses) (First Amendment) Regulations, 2023 dated 07.02.2023, and subsequent amendments and clarifications thereto, as applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 4.2.1. The SPD shall be required to obtain all information from the STU/ CTU/ STU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 4.2.2. Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 4.2.3. The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.4. In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 4.2.5. The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ CTU / concerned authority with regard to the ISTS connected Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the interconnection /Metering/Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to interconnection /Metering/Delivery point, will entirely be of the SPD, at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the interconnection /Metering/Delivery point shall also be the responsibility of the SPD.
4.2.2 4.2.3 The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the interconnection /Metering/Delivery Point shall be borne by the SPD and the same will not be reimbursed by NTPC or met by any other entity to whom this solar power is sold by NTPC. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection interconnection /Metering/Delivery Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement 4.2.7 At least 30 days before proposed commissioning date, the SPD shall be required to submit the connectivity letter from Central Transmission Utility (CTU), confirming technical feasibility of connectivity of the plant to the CTU substation. Copy of Long Term Access (LTA) agreement shall also be made submitted by the SPD through a dedicated transmission line. The entire cost one month prior to commissioning of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPDProject. In case of any delay in the project developer is unable to obtain connectivity to and/or LTA at least one month before proposed commissioning date for the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicableand it is established that the SPD has complied with the complete application formalities as per Clause 3.1.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU SPIA shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ CTU / concerned authority with regard to the ISTS connected Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the Interconnection/ Metering/Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to interconnection /Metering/Delivery point will entirely be of the SPD at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the interconnection /Metering/Delivery point shall be the responsibility of the SPD.
4.2.2 4.2.3 The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the interconnection /Metering/Delivery Point shall be borne by the SPD and the same will not be reimbursed by NHPC or met by the Discom(s). In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection interconnection /Metering/Delivery Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Government of India, from time to time, issues order for waiver of inter-state transmission system (ISTS) charges and losses on transmission of wind power till a certain date. In case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver, arising out of any reasons whatsoever, SECI shall bear no liability with respect to transmission charges and losses levied, if any. In case the SCD of the Project is before the date till above ISTS waiver is applicable, and if the Project is granted extension in the SCD on account of Force Majeure, or for delay on the part of the transmission provider in providing the transmission even after having taken the requisite steps in time; or on account of delays on the part of any Government Agency, and the Project is commissioned before the extended SCD; it will get benefit of waiver of inter-state transmission charges. However, in case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver/extended SCD as above, due to reasons attributable to the SPD, the liability of transmission charges and losses would be to the account of the SPD.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ CTU / concerned authority with regard to the ISTS connected Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the interconnection /Metering/Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to interconnection /Metering/Delivery point, will entirely be of the SPD, at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the interconnection /Metering/Delivery point shall be the responsibility of the SPD.
4.2.2 4.2.3 The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the interconnection /Metering/Delivery Point shall be borne by the SPD and the same will not be reimbursed by NTPC or met by the Discom(s). In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection interconnection /Metering/Delivery Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the SPIA/ STU/ CTU/ CTU / concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point.
4.2.2 The responsibility of getting connectivity with the transmission system up to Designated Substation as per the SPIA terms and conditions, will entirely be of the SPD, at its cost and responsibility. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall also be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of SPIA shall be the responsibility of the SPD.
4.2.2 4.2.3 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line as instructed by the SPIA. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point shall be borne by the SPD and the same will not be reimbursed by NTPC or met by the STU/Discom(s). In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
4.2.4 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU shall be the responsibility of the SPD. 4.2.5 All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 4.2.6 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his its own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Government of India from time to time issues order for waiver of inter-state transmission system (ISTS) charges and losses on transmission of wind/solar power till a certain date. In case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver, arising out of any reasons whatsoever, SECI shall bear no liability with respect to transmission charges and losses levied, if any.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
4.2.6 Government of India from time to time issues order for waiver of inter-state transmission system (ISTS) charges and losses on transmission of wind/solar power till a certain date. In case the SCD of the Project is before the date till above ISTS waiver is applicable, and if the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver due to Force Majeure event, the liability of transmission charges and losses would be shared between the SPD and Buying Utility(ies) in ratio of 50:50. However, in case the commissioning of the Project gets delayed beyond the applicable date of ISTS waiver due to reasons attributable to the SPD, the liability of transmission charges and losses would be that of the SPD.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ SPIA/STU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection PointPoint as per the SPIA terms and conditions, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU SPIA shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.[Not Used]
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission lineline as instructed by the SPIA. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 14 shall be applicable.
4.2.6 Interconnection Delivery point will be at the Grid substation and therefore from Generators substation/switchyard transmission line will be in scope of SPIA. The maintenance of Transmission system up to the Inter-connection Point shall be adhered to as per the Terms and Conditions of SPIA.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ SPIA/STU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection PointPoint as per the SPIA terms and conditions, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the terms and conditions of CTU/ STU SPIA shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.[Not Used]
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission lineline as instructed by the SPIA. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 14 shall be applicable.
4.2.6 Interconnection Delivery point will be at the Grid substation and therefore from Generators substation/switchyard transmission line will be in scope of SPIA. The maintenance of Transmission system up to the Inter-connection Point shall be
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ concerned authority STU/CTU/Concerned Authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation regulations/guidelines in relation to delay in commissioning of Project shall be payable entirely dealt by the SPD to the extent the delay is attributable to the and such amount claim by such agency(ies) shall be payable by SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 shall be applicable.Article
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from the STU/ CTU/ STU/CTU/concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost.
4.2.2 Penalties, fines and charges imposed by the CTU/ STU under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to the SPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions of CTU/ STU shall be the responsibility of the SPD. All costs and charges including but not limited to the wheeling charges and losses up to and including at the Interconnection Point associated with this arrangement will also be borne by the SPD.
4.2.4 In case of Pooling substation, losses in the transmission line shall be apportioned among the SPDs who share such a Pooling arrangementarrangement and duly signed by all SPDs, based on their monthly generation.
4.2.5 The arrangement of connectivity shall be made by the SPD through a dedicated transmission line. The entire cost of transmission including cost of construction of line, any other charges, losses etc. from the Project up to the Interconnection Point will be borne by the SPD. In case of any delay in connectivity to the Project and non- non-availability of Grid and Transmission System during Term of this Agreement, for reasons not attributable to the SPD, provisions of Article 4.9 4.10 shall be applicable.
Appears in 1 contract
Samples: Power Purchase Agreement