Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD‟s side of the Delivery Point to enable delivery of electricity at the Delivery Point. 4.2.2 The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the inter- connection point shall be the responsibility of the SPD. 4.2.3 The arrangement of connectivity can be made by the SPD through a dedicated transmission line which the SPD may construct itself or get constructed by STU or any other agency. The entire cost of transmission including cost of construction of line, wheeling charges, losses etc. from the Project upto the interconnection point will be borne by the SPD and will not be met by the STU. This connectivity can also be achieved through a shared line with any agency or any existing line of Discom or STU, provided the energy accounts are bifurcated and clearly demarcated for the power generated at solar project and are issued by the STU/ SLDC concerned. 4.2.4 The SPD may, however, shift interconnection point closer to its project if 33 kV (or above voltage level) substation comes closer to the Project during the tenure of PPA provided that the interconnection shall be maintained at 33 kV or above and energy at the project is clearly demarcated for the power generated at the solar project and energy accounts are issued by the STU/ SLDC concerned. The costs associated with this arrangement will also be borne by the SPD including the wheeling charges and losses up to the interconnect point. In case of nearby projects with Pooling point arrangement, the SPDs may decide to share the cost of transmission charges and other associated charges from the Pooling Point up to the Inter-connection Point, amongst themselves
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD‟s SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point.
4.2.2 The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the inter- connection point shall be the responsibility of the SPD.
4.2.3 The arrangement of connectivity can be made by the SPD through a dedicated transmission line which the SPD may construct itself or get constructed by STU or any other agency. The entire cost of transmission including cost of construction of line, wheeling charges, losses etc. from the Project upto the interconnection point will be borne by the SPD and will not be met by the STU. This connectivity can also be achieved through a shared line with any agency or any existing line of Discom or STU, provided the energy accounts are bifurcated and clearly demarcated for the power generated at solar project and are issued by the STU/ SLDC concerned.
4.2.4 The SPD may, however, shift interconnection point closer to its project if 33 kV (or above voltage level) substation comes closer to the Project during the tenure of PPA provided that the interconnection shall be maintained at 33 kV or above and energy at the project is clearly demarcated for the power generated at the solar project and energy accounts are issued by the STU/ SLDC concerned. The costs associated with this arrangement will also be borne by the SPD including the wheeling charges and losses up to the interconnect point. In case of nearby projects with Pooling point arrangement, the SPDs may decide to share the cost of transmission charges and other associated charges from the Pooling Point up to the Inter-connection Point, amongst themselves
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from STU/ CTU / concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD‟s SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point.
4.2.2 The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto up to the inter- inter-connection point shall be the responsibility of the SPD.
4.2.3 The arrangement of connectivity can be made by the SPD through a dedicated transmission line which the SPD may construct itself or get constructed by STU or any other agency. The entire cost of transmission including cost of construction of line, wheeling any other charges, losses etc. from the Project upto up to the interconnection point Interconnection Point will be borne by the SPD and will not be met by SPD. Subject to the STU. This acceptance of concerned STU / CTU / Authority / Agency (as applicable), this connectivity can also be achieved through a shared line with any agency or any existing line of Discom or STU/CTU, provided the energy accounts are bifurcated and clearly demarcated for the power generated at solar project and are issued by the STU/ SLDC concerned.
4.2.4 concerned and all the connected Projects have been selected under this RfS document. The SPD may, however, shift interconnection point closer shall not be entitled to its project if 33 kV (or above voltage level) substation comes closer any deemed generation in case of any delay in connectivity to the Project during the tenure of PPA provided that the interconnection shall be maintained at 33 kV or above and energy at the project is clearly demarcated for the power generated at the solar project and energy accounts are issued by the STU/ SLDC concerned. The costs associated with this arrangement will also be borne by the SPD including the wheeling charges and losses up to the interconnect point. In case of nearby projects with Pooling point arrangement, the SPDs may decide to share the cost of transmission charges and other associated charges from the Pooling Point up to the Inter-connection Point, amongst themselvesProject.
Appears in 2 contracts
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information from STU/ CTU / concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate Plant and all interconnection plant and apparatus interconnecting apparatus/ equipment on the SPD‟s SPD’s side of the Delivery Point to enable .enable delivery of electricity at the Delivery Point.
4.2.2 The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto up to the inter- inter-connection point shall be the responsibility of the SPD.
4.2.3 The arrangement of connectivity can be made by the SPD through a dedicated transmission line which the SPD may construct itself or get constructed by STU or any other agency. The entire cost of transmission including cost of construction of line, wheeling any other charges, losses etc. from the Project upto up to the interconnection point Interconnection Point will be borne by the SPD and will not be met by SPD. Subject to the STU. This acceptance of concerned STU / CTU / Authority / Agency (as applicable), this connectivity can also be achieved through a shared line with any agency or any existing line of Discom or STU/CTU, provided the energy accounts are bifurcated and clearly demarcated for the power generated at solar project and are issued by the STU/ SLDC concernedconcerned and all the connected Projects have been selected under this RfS document. The SPD shall not be entitled to any deemed generation in case of any delay in connectivity to the Project.
4.2.4 The Subject to the acceptance of concerned STU / CTU / Authority / Agency (as applicable), the SPD may, however, shift interconnection point closer to its project Project if 33 kV (or above voltage level) substation comes closer to the Project during the tenure of PPA provided that the interconnection shall be maintained at 33 kV or above and energy at the solar project is clearly demarcated for the power generated at the solar project and energy accounts are issued by the STU/ SLDC concerned. .
4.2.5 The all costs and charges including but not limited to the wheeling charges and losses up to the interconnect point associated with this arrangement will also be borne by the SPD including the wheeling charges and losses up to the interconnect pointSPD. In case of nearby projects with Pooling point arrangement, the SPDs may decide to share the cost of transmission charges and other associated charges from the Pooling Point up to the Inter-connection Point, amongst themselves.
4.2.6 In case of Pooling substation, losses in the transmission line between the Pooling substation and the substation of STU/CTU/any other transmission utility, shall be apportioned among the SPDs who share such a Pooling arrangement, based on their monthly generation.
Appears in 1 contract
Samples: Power Purchase Agreement
Information regarding Interconnection Facilities. 4.2.1 The SPD shall be required to obtain all information with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD‟s SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point.
4.2.2 The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the SPD. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system upto the inter- inter-connection point shall be the responsibility of the SPD.
4.2.3 The arrangement of connectivity can be made by the SPD through a dedicated transmission line which the SPD may construct itself or get constructed by STU or any other agency. The entire cost of transmission including cost of construction of line, wheeling any other charges, losses etc. from the Project upto the interconnection point will be borne by the SPD and will not be met by the STU. This connectivity can also be achieved through a shared line with any agency or any existing line of Discom or STU, provided the energy accounts are bifurcated and clearly demarcated for the power generated at solar project and are issued by the STU/ SLDC concerned.
4.2.4 The SPD may, however, shift interconnection point closer to its project if 33 kV (or above voltage level) substation comes closer to the Project during the tenure of PPA provided that the interconnection shall be maintained at 33 kV or above and energy at the project is clearly demarcated for the power generated at the solar project and energy accounts are issued by the STU/ SLDC concerned. The costs associated with this arrangement will also be borne by the SPD including the wheeling charges and losses up to the interconnect point. In case of nearby projects with Pooling point arrangement, the SPDs may decide to share the cost of transmission charges and other associated charges from the Pooling Point up to the Inter-connection Point, amongst themselves
Appears in 1 contract
Samples: Power Purchase Agreement