Inspections and Tests 26.1 The Supplier shall at its own expense and at no cost to the Procuring Entity carry out all such tests and/or inspections of the Goods and Related Services as are specified in the SCC. 26.2 The inspections and tests may be conducted on the premises of the Supplier or its Subcontractor, at point of delivery, and/or at the Goods' final destination, or in another place in Kenya as specified in the SCC. Subject to GCC Sub-Clause 26.3, if conducted on the premises of the Supplier or its Subcontractor, all reasonable facilities and assistance, including access to drawings and production data, shall be furnished to the inspectors at no charge to the Procuring Entity. 26.3 The Procuring Entity or its designated representative shall be entitled to attend the tests and/or inspections referred to in GCC Sub-Clause 26.2, provided that the Procuring Entity bear all of its own costs and expenses incurred in connection with such attendance including, but not limited to, all travelling and board and lodging expenses. 26.4 Whenever the Supplier is ready to carry out any such test and inspection, it shall give a reasonable advance notice, including the place and time, to the Procuring Entity. The Supplier shall obtain from any relevant third party or manufacturer any necessary permission or consent to enable the Procuring Entity or its designated representative to attend the test and/or inspection. 26.5 The Procuring Entity may require the Supplier to carry out any test and/or inspection not required by the Contract but deemed necessary to verify that the characteristics and performance of the Goods comply with the technical specifications codes and standards under the Contract, provided that the Supplier's reasonable costs and expenses incurred in the carrying out of such test and/or inspection shall be added to the Contract Price. Further, if such test and/or inspection impedes the progress of manufacturing and/or the Supplier's performance of its other obligations under the Contract, due allowance will be made in respect of the Delivery Dates and Completion Dates and the other obligations so affected. 26.6 The Supplier shall provide the Procuring Entity with a report of the results of any such test and/or inspection. 26.7 The Procuring Entity may reject any Goods or any part thereof that fail to pass any test and/or inspection or do not conform to the specifications. The Supplier shall either rectify or replace such rejected Goods or parts thereof or make alterations necessary to meet the specifications at no cost to the Procuring Entity, and shall repeat the test and/or inspection, at no cost to the Procuring Entity, upon giving a notice pursuant to GCC Sub- Clause 26.4. 26.8 The Supplier agrees that neither the execution of a test and/or inspection of the Goods or any part thereof, nor the attendance by the Procuring Entity or its representative, nor the issue of any report pursuant to GCC Sub-Clause 26.6, shall release the Supplier from any warranties or other obligations under the Contract.
Inspection and Tests 3.8.1 The Procuring entity or its representative shall have the right to inspect and/or to test the goods to confirm their conformity to the Contract specifications. The Procuring entity shall notify the tenderer in writing in a timely manner, of the identity of any representatives retained for these purposes. 3.8.2 The inspections and tests may be conducted in the premises of the tenderer or its subcontractor(s), at point of delivery, and/or at the Goods’ final destination If conducted on the premises of the tenderer or its subcontractor(s), all reasonable facilities and assistance, including access to drawings and production data, shall be furnished to the inspectors at no charge to the Procuring entity. 3.8.3 Should any inspected or tested goods fail to conform to the Specifications, the Procuring entity may reject the equipment, and the tenderer shall either replace the rejected equipment or make alterations necessary to make specification requirements free of costs to the Procuring entity. 3.8.4 The Procuring entity’s right to inspect, test and where necessary, reject the goods after the Goods’ arrival shall in no way be limited or waived by reason of the equipment having previously been inspected, tested and passed by the Procuring entity or its representative prior to the equipment delivery. 3.8.5 Nothing in paragraph 3.8 shall in any way release the tenderer from any warranty or other obligations under this Contract.
Inspection and Testing Each Constructing Entity shall cause inspection and testing of the Interconnection Facilities that it constructs in accordance with the provisions of this section. The Construction Parties acknowledge and agree that inspection and testing of facilities may be undertaken as facilities are completed and need not await completion of all of the facilities that a Constructing Entity is building.
Investigations and Remediations Lessor shall retain the responsibility and pay for any investigations or remediation measures required by governmental entities having jurisdiction with respect to the existence of Hazardous Substances on the Premises prior to the Start Date, unless such remediation measure is required as a result of Lessee's use (including "Alterations", as defined in Paragraph 7.3(a) below) of the Premises, in which event Lessee shall be responsible for such payment. Lessee shall cooperate fully in any such activities at the request of Lessor, including allowing Lessor and Lessor's agents to have reasonable access to the Premises at reasonable times in order to carry out Lessor's investigative and remedial responsibilities.
INSPECTIONS AND AUDITS 30 A. ADMINISTRATOR, any authorized representative of COUNTY, any authorized representative 31 of the State of California, the Secretary of the United States Department of Health and Human Services, 32 the Comptroller General of the United States, or any other of their authorized representatives, shall have 33 access to any books, documents, and records, including but not limited to, financial statements, general 34 ledgers, relevant accounting systems, medical and client records, of CONTRACTOR that are directly 35 pertinent to this Agreement, for the purpose of responding to a beneficiary complaint or conducting an 36 audit, review, evaluation, or examination, or making transcripts during the periods of retention set forth 37 in the Records Management and Maintenance Paragraph of this Agreement. Such persons may at all 1 reasonable times inspect or otherwise evaluate the services provided pursuant to this Agreement, and the 2 premises in which they are provided. 3 B. CONTRACTOR shall actively participate and cooperate with any person specified in 4 Subparagraph A. above in any evaluation or monitoring of the services provided pursuant to this 5 Agreement, and shall provide the above–mentioned persons adequate office space to conduct such 6 evaluation or monitoring. 7 C. AUDIT RESPONSE 8 1. Following an audit report, in the event of non–compliance with applicable laws and 9 regulations governing funds provided through this Agreement, COUNTY may terminate this Agreement 10 as provided for in the Termination Paragraph or direct CONTRACTOR to immediately implement 11 appropriate corrective action. A plan of corrective action shall be submitted to ADMINISTRATOR in 12 writing within thirty (30) calendar days after receiving notice from ADMINISTRATOR. 13 2. If the audit reveals that money is payable from one party to the other, that is, reimbursement 14 by CONTRACTOR to COUNTY, or payment of sums due from COUNTY to CONTRACTOR, said 15 funds shall be due and payable from one party to the other within sixty (60) calendar days of receipt of 16 the audit results. If reimbursement is due from CONTRACTOR to COUNTY, and such reimbursement 17 is not received within said sixty (60) calendar days, COUNTY may, in addition to any other remedies 18 provided by law, reduce any amount owed CONTRACTOR by an amount not to exceed the 19 reimbursement due COUNTY. 20 D. CONTRACTOR shall retain a licensed certified public accountant, who will prepare an annual 21 Single Audit as required by 31 USC 7501 – 7507, as well as its implementing regulations under 2 CFR 22 Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal 23 Awards. CONTRACTOR shall forward the Single Audit to ADMINISTRATOR within fourteen (14) 24 calendar days of receipt. 25 E. CONTRACTOR shall forward to ADMINISTRATOR a copy of any audit report within 26 fourteen (14) calendar days of receipt. Such audit shall include, but not be limited to, management, 27 financial, programmatic or any other type of audit of CONTRACTOR’s operations, whether or not the 28 cost of such operation or audit is reimbursed in whole or in part through this Agreement. 29
Inspection of Facilities In order to meet their respective obligations under this Agreement, any Party may view or inspect facilities owned by another Party. Provided that reasonable notice is given, a Party shall not unreasonably deny access to relevant facilities for viewing or inspection by the requesting Party.
Audits/Inspections Contractor agrees to permit the County’s Auditor-Controller or the Auditor- Controller’s authorized representative (including auditors from a private auditing firm hired by the County) access during normal working hours to all books, accounts, records, reports, files, financial records, supporting documentation, including payroll and accounts payable/receivable records, and other papers or property of Contractor for the purpose of auditing or inspecting any aspect of performance under this Contract. The inspection and/or audit will be confined to those matters connected with the performance of the Contract including, but not limited to, the costs of administering the Contract. The County will provide reasonable notice of such an audit or inspection. The County reserves the right to audit and verify the Contractor’s records before final payment is made. Contractor agrees to maintain such records for possible audit for a minimum of three years after final payment, unless a longer period of records retention is stipulated under this Contract or by law. Contractor agrees to allow interviews of any employees or others who might reasonably have information related to such records. Further, Contractor agrees to include a similar right to the County to audit records and interview staff of any subcontractor related to performance of this Contract. Should the Contractor cease to exist as a legal entity, the Contractor’s records pertaining to this Contract shall be forwarded to the County’s project manager.
Maintaining Records; Access to Properties and Inspections Maintain financial records in accordance with GAAP and, upon reasonable notice, permit any representatives designated by the Administrative Agent or any Lender to visit and inspect the financial records and the properties of the Borrower or any Significant Subsidiary during normal business hours and to discuss the affairs, finances and condition of the Borrower or any Significant Subsidiary with the officers thereof and independent accountants therefor.
Response/Compliance with Audit or Inspection Findings A. Grantee must act to ensure its and its Subcontractors’ compliance with all corrections necessary to address any finding of noncompliance with any law, regulation, audit requirement, or generally accepted accounting principle, or any other deficiency identified in any audit, review, inspection or investigation of the Grant Agreement and the services and Deliverables provided. Any such correction will be at Grantee’s or its Subcontractor's sole expense. Whether Xxxxxxx's action corrects the noncompliance shall be solely the decision of the System Agency. B. As part of the services, Grantee must provide to HHS upon request a copy of those portions of Grantee's and its Subcontractors' internal audit reports relating to the services and Deliverables provided to the State under the Grant Agreement. C. Grantee shall include the requirement to provide to System Agency (and any of its duly authorized federal, state, or local authorities) internal audit reports related to this Grant Agreement in any Subcontract it awards. Upon request by System Agency, Grantee shall enforce this requirement against its Subcontractor. Further, Grantee shall include in any Subcontract it awards a requirement that all Subcontractor Subcontracts must also include these provisions.
Records and Audit/Inspections 6.13.1 A-E shall keep an accurate record of time expended by A-E and/or consultants employed by A-E in the performance of this CONTRACT. 6.13.2 Within ten (10) days of COUNTY's written request, A-E shall allow COUNTY or authorized State or Federal agencies or any duly authorized representative to have the right to access, examine, audit, excerpt, copy or transcribe any pertinent transaction, activity, time cards or other records relating to this CONTRACT. 6.13.3 A-E shall keep such material, including all pertinent cost accounting, financial records and proprietary data for a period of three (3) years after termination or completion of the CONTRACT or until resolution of any claim or dispute between the PARTIES, whichever is later. 6.13.4 Should A-E cease to exist as a legal entity, records pertaining to this CONTRACT shall be forwarded within a reasonable period of time not to exceed sixty (60) days to its successor in interest or surviving entity in a merger or acquisition, or, in the event of liquidation, to COUNTY.