Interconnection Facilities Study Procedures. Transmission Provider shall coordinate the Interconnection Facilities Study with any Affected System pursuant to Section 3.6. Transmission Provider shall utilize existing studies to the extent practicable in performing the Interconnection Facilities Study. Transmission Provider shall use Reasonable Efforts to complete the study and issue a draft Interconnection Facilities Study report to Interconnection Customer within the following number of Calendar Days after receipt of an executed Interconnection Facilities Study Agreement: ninety (90) Calendar Days, with no more than a +/- 20 percent cost estimate contained in the report; or one hundred fifty (150) Calendar Days, if Interconnection Customer requests a +/- 10 percent cost estimate. At the request of Interconnection Customer or at any time Transmission Provider determines that it will not meet the required time frame for completing the Interconnection Facilities Study, Transmission Provider shall notify Interconnection Customer as to the schedule status of the Interconnection Facilities Study. If Transmission Provider is unable to complete the Interconnection Facilities Study and issue a draft Interconnection Facilities Study report within the time required, it shall notify Interconnection Customer and provide an estimated completion date and an explanation of the reasons why additional time is required.
Appears in 4 contracts
Samples: Generator Interconnection Agreement, Confidentiality Agreement, Generator Interconnection Agreement
Interconnection Facilities Study Procedures. Transmission Provider shall coordinate the Interconnection Facilities Study with any Affected System pursuant to Section 3.63.56 above. Transmission Provider shall utilize existing studies to the extent practicable in performing the Interconnection Facilities Study. Transmission Provider shall use Reasonable Efforts to complete the study and issue a draft Interconnection Facilities Study report to Interconnection Customer within the following number of Calendar Days days after receipt of an executed notice from the Interconnection Facilities Study AgreementCustomer to proceed pursuant to Section 8.2: ninety (90) Calendar Days, with no more than a +/- 20 percent cost estimate contained in the report; or one hundred fifty eighty (150180) Calendar Days, if Interconnection Customer requests a +/- 10 percent cost estimate. At the request of Interconnection Customer or at any time Transmission Provider determines that it will not meet the required time frame for completing the Interconnection Facilities Study, Transmission Provider shall notify Interconnection Customer as to the schedule status of the Interconnection Facilities Study. If Transmission Provider is unable to complete the Interconnection Facilities Study and issue a draft Interconnection Facilities Study report within the time required, it shall notify Interconnection Customer and provide an estimated completion date and an explanation of the reasons why additional time is required.
Appears in 1 contract
Samples: www.bchydro.com