Interconnection of the Project. Interconnection of the Project to Utility's distribution system shall be made after the following conditions have been satisfied: 2.2.1 Both Parties have declared their Interconnection Facilities ready for service; 2.2.2 Applicant has met the design, specifications, installation and construction requirements of the second paragraph of Subsection 2.1, Authority for Construction; 2.2.3 Applicant has provided adequate protective equipment to protect the equipment and service of Utility from damage or interruption from electrical faults occurring at the Project; 2.2.4 Utility has tested and accepted the billing meters and associated telemetry for the collection of the metered data required pursuant to Exhibit 1 – Scope of Facilities, Subsection 1.3;
Appears in 1 contract
Interconnection of the Project. Interconnection of the Project to Utility's Consumers' distribution system shall be made after the following conditions have been satisfied:
2.2.1 Both Parties have declared their Interconnection Facilities ready for service;
2.2.2 Applicant Project Developer has met the design, specifications, installation and construction requirements of the second paragraph of Subsection 2.1, Authority for Construction;
2.2.3 Applicant Project Developer has provided adequate protective equipment to protect the equipment and service of Utility Consumers from damage or interruption from electrical faults occurring at the Project;
2.2.4 Utility Consumers has tested and accepted the billing meters and associated telemetry for the collection of the metered data required pursuant to Exhibit 1 – Scope of Facilities, Subsection 1.3;
Appears in 1 contract
Interconnection of the Project. Interconnection of the Project to Utility's Consumers' distribution system shall be made after the following conditions have been satisfied:
2.2.1 2.3.1 Both Parties have declared their Interconnection Facilities ready for service;
2.2.2 Applicant 2.3.2 Project Developer has met the design, specifications, installation and construction requirements of the second paragraph of Subsection 2.1, Authority for Construction;
2.2.3 Applicant 2.3.3 Project Developer has provided adequate protective equipment to protect the equipment and service of Utility Consumers from damage or interruption from electrical faults occurring at the Project;
2.2.4 Utility 2.3.4 Consumers has tested and accepted the billing meters and associated telemetry for the collection of the metered data required pursuant to Exhibit 1 – Scope of Facilities, Subsection 1.3;
Appears in 1 contract
Interconnection of the Project. Interconnection of the Project to Utility's ’s distribution system shall be made after the following conditions have been satisfied:
2.2.1 2.3.1 Both Parties have declared their Interconnection Facilities ready for service;
2.2.2 Applicant 2.3.2 Interconnection Customer has met the design, specifications, installation and construction requirements of the second paragraph of Subsection 2.1, Authority for Construction;
2.2.3 Applicant 2.3.3 Interconnection Customer has provided adequate protective equipment to protect the equipment and service of Utility from damage or interruption from electrical faults occurring at the Project;
2.2.4 2.3.4 Utility has tested and accepted the billing meters and associated telemetry for the collection of the metered data required pursuant to Exhibit 1 – Scope of Facilities, Subsection 1.3;