Interconnection Party Sample Clauses

Interconnection Party. Transmission Provider, Interconnection Customer, or the Interconnected Transmission Owner. Interconnection Parties shall mean all of them.
AutoNDA by SimpleDocs
Interconnection Party. Legal Name of the Interconnection Party (or, if an individual, individual's name) Name: Account Number: Contact Name: Title: E-Mail Address: Mailing Address: Telephone: Facility Location (if different from above): Address: County: Inverter Manufacturer: Model Nameplate Rating: (kW) (kVA) (AC Volts) System Design Capacity: (kW) (kVA) Single Phase Three Phase Prime Mover: Photovoltaic 🗌 Reciprocating Engine �� Fuel Cell 🗌 Turbine 🗌 Other Energy Source: Solar 🗌 Wind 🗌 Hydro 🗌 Diesel 🗌 Natural Gas 🗌 Fuel Oil 🗌 Other (describe) Is the equipment UL 1741 Listed? Yes No If Yes, attach manufacturer’s cut-sheet showing UL 1741 listing Estimated Installation Date: Estimated In-Service Date: The 20 kW Inverter Process is available only for inverter-based Generating Facilities no larger than 20 kW that meet the codes, standards, and certification requirements of Attachments 5 and 6 of the Cooperative’s Standard Generator Interconnection Procedures, Forms, and Agreements (“SGIP”), or the Cooperative has reviewed the design or tested the proposed Generating Facility and is satisfied that it is safe to operate. List components of the Generating Facility equipment package that are currently certified: Number Equipment Type Certifying Entity 1.

Related to Interconnection Party

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Interconnection Customer Authority Consistent with Good Utility Practice, this LGIA, and the CAISO Tariff, the Interconnection Customer may take actions or inactions with regard to the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities,

  • Interconnection Customer Provided Services The services provided by Interconnection Customer under this LGIA are set forth in Article 9.6 and Article 13.5. 1. Interconnection Customer shall be paid for such services in accordance with Article 11.6.

  • Interconnection Service Interconnection Service allows the Interconnection Customer to connect the Large Generating Facility to the Participating TO’s Transmission System and be eligible to deliver the Large Generating Facility’s output using the available capacity of the CAISO Controlled Grid. To the extent the Interconnection Customer wants to receive Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct.

  • Interconnection Customer Obligations The Interconnection Customer shall maintain the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA.