Equipment Failures In the event of equipment failures beyond the Administrator's control, the Administrator shall take reasonable and prompt steps to minimize service interruptions but shall have no liability with respect thereto. The Administrator shall develop and maintain a plan for recovery from equipment failures which may include contractual arrangements with appropriate parties making reasonable provision for emergency use of electronic data processing equipment to the extent appropriate equipment is available.
Payment Failure Any Credit Party (i) fails to pay any principal when due under this Agreement or (ii) fails to pay, within three Business Days of when due, any other amount due under this Agreement or any other Credit Document, including payments of interest, fees, reimbursements, and indemnifications;
Launch Customer shall use commercially reasonable efforts to begin distribution of the Google Desktop Applications promptly following the launch of the Desktop Portal.
Commissioning preparation of a system or systems to allow hydrocarbons or other process fluids to be safely introduced into the system or systems for processing. In this phase testing will focus on systems, including utilities.
Monitoring System In each case in which the Custodian has exercised delegated authority to place Assets with a Foreign Custodian, the Custodian shall establish a system, to re-assess or re-evaluate selected Foreign Custodians, at least annually in accordance with Rule 17f-5(c)(3).
Project Completion Within five (5) days after the delivery by Supplier to Purchaser of a Commissioning Certificate for the Project’s final Turbine, Supplier shall also deliver to Purchaser a completion certificate for all Turbines in the Project (the “Project Completion Certificate”), in the form attached hereto as Exhibit N, together with a list of any remaining Punch List Work on any Turbine, a schedule for completing the Punch List Work and an estimate of the cost of each item of Punch List Work. Supplier shall thereafter promptly complete all Punch List Work.
Warranty Period The warranties set forth in Clauses 12.1.1 and 12.1.2 shall be limited to those defects that become apparent within **** after Delivery of the affected Aircraft (the “Warranty Period”).
Performance Tests Contractor shall perform Performance Tests in accordance with Section 11.2 of the Agreement and Attachment S.
Final Completion 6.5.1 Final Completion of the Work shall be achieved within ninety (90) Days after the earlier of the actual date of Substantial Completion or the Scheduled Substantial Completion Date (the “Final Completion Date”).
Epidemic Failure In the event that CONTRACTUAL PRODUCTS under warranty have the same or similar functional defect during a time period of three (3) months and the number of defected CONTRACTUAL PRODUCTS exceed [***] of the quantity delivered within this time period, this [***] = CERTAIN INFORMATION ON THIS PAGE HAS BEEN OMITTED AND FILED SEPARATELY WITH THE COMMISSION. CONFIDENTIAL TREATMENT HAS BEEN REQUESTED WITH RESPECT TO THE OMITTED PORTIONS. shall be an “Epidemic Failure” as mentioned in the following. The term “Epidemic Failure” shall exclusively apply to delivered CONTRACTUAL PRODUCTS with a number of pieces of more than ten thousand (>10.000) during three (3) months. If either CONTRACTUAL PARTY learns of the existence or likely existence of an Epidemic Failure, then such CONTRACTUAL PARTY will inform the other CONTRACTUAL PARTY as soon as possible. The CONTRACTUAL PARTIES shall then work together to jointly devise a containment action plan. As soon thereafter as reasonably possible, the CONTRACTUAL PARTIES will develop a corrective action plan to remedy the Epidemic Failure. Phoenix Contact shall use its best efforts to implement such remedy as quickly as possible at Phoenix Contact’s own expense, which efforts shall include receiving all shipments of affected Product back (freight collect), repairing or replacing all such affected Products in accordance with the agreed remedy devised by the Parties, shipping the repaired or replaced Products back to ENPHASE at Phoenix Contact’s expense, and implementing the agreed remedy in all newly manufactured Products. Phoenix Contact shall be responsible for the reasonable following costs and expenses actually incurred and substantiated as a result of all aspects of implementing the agreed remedy on the affected Products: reasonable costs of the retrieval, packing, shipping and transportation of such Products, and the re-deployment of repaired or replacement Products (including all labor, consulting, contractor and the like charges, incurred by ENPHASE, only if Phoenix Contact has agreed in writing that ENPHASE is allowed to do the aforementioned activities). For the avoidance of doubt all damages defined in Article 11.4 shall be direct damages and shall be subject to Article 14.2.