Common use of Limitation on Change Orders Clause in Contracts

Limitation on Change Orders. Change Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.3. Notwithstanding anything to the contrary, other than to the extent resulting from a Force Majeure Event occurring after the Effective Date, in no event shall any Site Condition give rise to a Change Order.

Appears in 2 contracts

Samples: Build Transfer Agreement, Engineering, Procurement and Construction Agreement

AutoNDA by SimpleDocs

Limitation on Change Orders. Change Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.110.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 10.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.310.3. Notwithstanding anything to the contrary, other than to the extent resulting from a Force Majeure Event occurring after the Effective Date, in no event shall any Site Condition give rise to a Change Order.

Appears in 2 contracts

Samples: Build Transfer Agreement, Procurement and Construction Agreement

Limitation on Change Orders. Change Changes Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.110.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 10.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.310.3. Notwithstanding anything to the contrary, other than to the extent resulting from a Force Majeure Event occurring after the Effective Date, in no event shall any Site Condition give rise to a Change Order*** *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Sunpower Corp)

Limitation on Change Orders. Change Changes Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.110.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 10.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.310.3. Notwithstanding anything to the contrary, other than to the extent resulting from any *** arise by reason of a Force Majeure Event occurring that occurs after the Effective Date, in no event shall any Site Condition *** give rise to a Change Order. *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION.

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)

AutoNDA by SimpleDocs

Limitation on Change Orders. Change Changes Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.110.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 10.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.310.3. Notwithstanding anything to the contrary, other than to the extent resulting from a Force Majeure Event occurring after the Effective Date, in no event shall any Site Condition give rise to a Change Order.***

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Sunpower Corp)

Limitation on Change Orders. Change Changes Orders shall be limited to (i) changes requested by Owner in accordance with Section 9.110.1, (ii) changes requested by Contractor and mutually agreed to by the Parties in accordance with Section 9.2 10.2 and (iii) changes in connection with mandatory Change Orders in accordance with Section 9.310.3. Notwithstanding anything to the contrary, other than to the extent resulting from any *** arise by reason of a Force Majeure Event occurring that occurs after the Effective Date, in no event shall any Site Condition *** give rise to a Change Order.

Appears in 1 contract

Samples: Procurement and Construction Agreement (Sunpower Corp)